Agenda item
INTERNAL AUDIT OF WEST RHYL COASTAL DEFENCE SCHEME PHASE 3
To consider a report by the Head of Internal Audit (copy
enclosed) on the recent
Internal Audit report on the Coastal Defence project that received a ‘Low’
assurance rating.
Minutes:
A
report by the Head of Internal Audit (HIA), which detailed the recent Internal Audit report on the Coastal
Defence project that received a ‘Low’ assurance rating, had been circulated
previously.
The HIA explained that
the Committee received an Internal Audit Progress report for each meeting which
included details of Internal Audit reports issued. These were normally ‘High’ or ‘Medium’
assurance reports. However, when a ‘Low’
or ‘No’ assurance rating report was issued the Committee received the report,
as part of its agenda, to ensure that it was fully aware of the position and
were afforded the opportunity to discuss the improvements to be implemented
with the relevant manager. The full Internal Audit report had been
included as Appendix 1.
The Senior Auditor
explained that the complex audit which had been undertaken had focused mainly
on the procurement aspect of the project.
A contract audit
checklist had been developed with the involvement of the Collaborative
Procurement Service that covered the following areas:-
·
Governance
·
Pre-tendering
·
Financing
·
Tendering
·
Management
of the Contract
The SA confirmed that the remit had not been to comment on the success
of the West Rhyl Coastal Defence Phase 3 scheme, and it was explained that this
was the first project to be reviewed using the checklist. She referred to the following issues and
areas highlighted in the Action Pan, Appendix 1, which included:-
-
The need to take into account the history of the
programme of work, which included Phases 1 and 2, and two tenders having
increased the complexity of the audit.
-
The
unavailability of written confirmation of WG’s timescale to complete the flood
defence work, which had been completed retrospectively at the conclusion of the
review.
-
Contract documentation with the main contractor
having been unobtainable until August, 2015.
-
Corporate issues having been highlighted in respect
of the role of finance, procurement and legal issues.
The Head of Highways and Environmental Services (HHES) provided the
following information pertaining to the project:-
-
Denbighshire had worked closely with Welsh
Government to protect a significant number of homes on a reasonable and
inexpensive budget utilising an innovative solution to address the problems
being encountered.
-
Details were provided of the materials utilised
which had been specified by Denbighshire.
-
The programme of work had been undertaken in three
large manageable phases. Work had
commenced in West Rhyl, and not Splash Point, as Phases 1 and 2 had been
identified as high risk areas.
-
Confirmation was provided that although a
Trunk Road Agency framework was utilised, they were not involved in the
procurement process
-
The work carried out in East Rhyl had been an interim
scheme to provide protection for the area, and a much larger scheme would be
undertaken.
-
Details pertaining to the tender process were
provided, particular reference was made to the acceptance and signing of
contracts. Members were informed that procurement
was now undertaken electronically and it was highlighted that the timing aspect
of the process was critical in relation to the commencement of the works.
The HLHRDS outlined the importance and timing aspect of the
documentation process, and it was confirmed that although letters of intent
were still utilised they were not a substitute for a formal contract. The HLHRDS explained that it was important to
ensure that work did not commence on site prior to the completion of the
electronic procurement process.
The Programme
Manager Procurement (PMP) provided an assurance that the revised CPR’s would
address the issues of concerns raised, and the HLHRDS that the early
involvement of Legal and Procurement Services would be pivotal in the future.
During the ensuing discussion Members agreed that, following the
identified completion dates in October, 2016, a progress report be presented to
the Committee in January, 2017 in respect of the Rhyl Coastal Defence Scheme.
RESOLVED – that the
Corporate Governance Committee:-
(a)
receives and notes the Internal Audit report.
(b)
confirms the effective implementation of the Action
Plan, within the agreed timescales, and
(c)
agrees that a progress report be presented to the
January, 2017 meeting of the Committee.
(SP, IB, LH to Action)
Supporting documents: