BUDGET PROCESS 2015/16
To consider a report by the Chief Finance Officer, which provides an update on the process to deliver the revenue budget for 2016/17 (copy enclosed).
Minutes:
A
report by the Chief Finance Officer (CFO), which provided an update on the
process to deliver the revenue budget for 2016/17, had been circulated
previously.
Councillor J.
Thompson-Hill, assisted by the Chief Accountant (CA), provided a detailed
summary of the report which included the following information:-
·
The
latest progress with the budget setting process had been presented to a Member
Budget Workshop on the 14th December, 2015. An outline of the range of savings proposals
considered had been outlined.
·
The
draft Welsh Government budget and the Provisional Settlement to local
government had been announced later than usual this year as a consequence of
the timing of the UK Government’s Autumn Spending Review. This had been factored into the budget
planning process and resulted in the package of proposals being taken for
approval in December. The package
totalling £1.2m contained efficiency savings and technical adjustments, but did
not include any proposals to cut services or increase charges.
·
The
implications of the Local Government Settlement for 2015/16 had been summarised
in the report, with the Settlement being much better than expected.
·
A
report to Council in December had detailed the latest budget position and
assumptions indicated a remaining budget gap of £2m. Details had been provided at the budget
workshop with a summary included in the report.
·
Details
of the changes to the Settlement value, which allowed for a proposal to lower
the level of proposed Council Tax rise from 2.75% to an average of 1.5%, had
been included in the report.
·
The
assumptions applied had resulted in a positive funding position of £480k, with
the Settlement for 2016/17 having been better than expected for one-year. A table summarising the budget planning
position for future years had been provided.
Details of risks had been outlined, together with, the actions
implemented to mitigate them.
·
The
Final Local Government Settlement would not be published until March. However, assurances had been provided that
there should be no negative movement between the Provisional Draft and Final
Settlement values. The final Welsh
Government budget would be put before the Senedd on
the 8th March.
·
The
Freedoms & Flexibilities process had ended with the setting of the
2016/17. Monitoring of budget
performance would continue to be reported to cabinet, with the Cutting Our
Cloth Task & Finish Group monitoring the impact of budget decisions.
·
It was
confirmed that a new budget process would be developed for 2017/18.
·
The
final phase of the two-year Freedoms & Flexibilities budget process had
been presented. The vast majority of
savings, over 80%, had been efficiency or modernisation savings resulting in a
less significant impact on services to the public.
·
It was
explained that the aim of the budget process had been to ensure that the
Council delivered a balanced budget. It
was likely that funding reductions to LA’s in Wales would continue in the
medium term, with budget decisions becoming more difficult and requiring a
longer lead-in time to deliver.
Councillor
Thompson-Hill outlined the timescales pertaining to the budget reporting
process and sought guidance regarding the timing of the submission of future
reports. The Chair felt that it would be
beneficial if the current process of the inclusion of a standard budget process
business item on each agenda of the Committee be continued, along with the
provision of Member Budget Workshops. He
also felt there was a need to increase consultation with the public and
acknowledged that there were differing views regarding the adoption of a new
consultation process. It was suggested
and agreed that the respective Political Groups be contacted with a view to
encouraging Members to put forward their views and suggestions in respect of
the budget process. Councillor S.A.
Davies expressed his support for the continuation of the current process, and
highlighted the need and importance of scrutinising the adopted
mechanisms. Mr P. Whitham
supported the view expressed and suggested that failure to continue to progress
could present a corporate risk to the Authority.
The HLHRDS outlined
the possible technical issues and constraints which could arise around finance
with regard to the progress of the Local Government (Wales) Bill, and the
subsequent merging of Local Authorities.
Mr P. Whitham suggested that as the report presented the final
phase of the two-year Freedoms & Flexibilities budget process a post
completion review should be undertaken to ascertain the aims, achievements,
successes and lessons learned with regard to assisting with future
progress. The Chair made reference to
the Cutting Our Cloth Task and Finish Group which monitored the impact of the
budget decisions taken as part of the process, this being achieved through
evidence gathering and examining the mechanisms utilised and adopted.
RESOLVED – that the
Corporate Governance Committee:-
(a)
receives and notes
the contents of the report on the latest update.
(b)
request that the Political Groups encourage Members to
put forward their views, and
(c)
agrees that a
further update report be presented to the March, 2016 meeting of the Committee.
(RW, SG, GW to Action)