Agenda item
NOVA CENTRE REDEVELOPMENT
To consider a report by the Head of Communication, Marketing and Leisure (copy enclosed) which considers the proposals for the redevelopment of the Prestatyn Nova Centre.
Minutes:
A copy of a report by the Head of
Communication, Marketing and Leisure (HCML), which sought a decision by Council to approve the recommendation of the
Strategic Investment Group to proceed with the redevelopment of the Nova
Centre, Prestatyn, had been circulated prior
to the meeting. The Chair welcomed
representatives of Alliance Leisure
Services (ALS) to the meeting.
With the aid of a PowerPoint presentation the HCML introduced the
report. He explained that Cabinet had in
January, 2014 considered the findings of a due diligence review into Clwyd Leisure Ltd (CLL), and
concluded that it would be too great a risk to take over the company. It was decided to cease funding CLL from the 1st April, 2014, due to
concerns over the quality and level of service provision, and CLL subsequently
ceased trading with immediate effect.
A report to Cabinet in March, 2014
outlined the recommendations
arising from a detailed appraisal of the building conditions and the cost
benefit analysis in respect of the different interim management options for the
facilities, whilst the
business case for a much improved leisure offer on the coast was developed
further. Cabinet agreed to
recommend that the Nova Centre remained closed pending agreement of the ALS
redevelopment proposals in May, 2014.
A feasibility exercise and outline business case for the proposed
redevelopment of the Centre had been commissioned for consideration by the
Strategic Investment Group (SIG), and details of the process had been
provided. A feasibility and outline
business case was presented to the SIG and Cabinet in June, 2014 to secure
funding to take the project forward to detailed design. Progression to the next stage, and the
awarding of 108k for the detailed design stages in order to establish cost
certainty for the project, had been approved.
ALS in partnership with
Denbighshire completed all detailed surveys and provided the SIG with detailed
costs based on a mix of facilities, as agreed in the original feasibility
brief, Appendix 1. Members were informed
that the facility would be self-sufficient by servicing its own energy costs.
Detailed surveys identified issues which needed to be resolved to ensure
the long term sustainability of the building for the term of the business case,
based on known income potential, and the Councils financial commitment. Mechanical and electrical plant required
replacing, and a roofing survey identified a host of issues. The increase in costs from outline to detail
design stage represented a 15% increase in overall development costs. This would be containable within the overall
envelope of affordability over the business case term.
It was explained that the
development was a major strand of the Council’s vision for an improved leisure
and tourism offer along the coast, as set out in the Economic Ambition
Strategy. The BIG Plan 2011–2014 aimed to achieve a number of
outcomes, particularly the desire for people in Denbighshire to have healthy
lifestyles.
The costs pre-detailed design had been approximately £3.6 million. The revised costs, due to the roofing and
M&E requirements, had increased to £4,217,001. Officers and the AL project team had been
through a vigorous ‘value engineering process’ reviewing the costs and
specification to reduce the costs without compromising the whole
development. The original business case
identified a total of £256,311 to service the overall borrowing required for
the development. Due to an increase in
capital required for the development, the prudential borrowing costs had
increased to an annualised payment of £284,680, representing a total increase
of £28,369 per annum. This was confined within the affordability of
the project and been fully considered and scrutinised by both the SIG and
Coastal Facilities Board. The HCML
confirmed that the project was now at cost certainty and pending any requested
changes to the scheme risks would be borne by ALS.
A budget forecast had been included in Appendix 2, with a financial
commentary in Appendix 3, and a full financial statement from our Finance and
Assurance Manager in Appendix 4. The
budget forecast indicated an operating loss in year 1 of £68,223, a loss of
£6,447in year 2, and by year 3 a surplus of £11,785. The Centre would have made a £23,440
operational loss over a five year period, over and above the resources
available for the running of the facility, however this assumed only realising
just over 70% of the overall latent demand.
In the event of the development not proceeding
the building was likely to remain in its current condition until further
options were explored, and the Centre would cost approximately £71,000 per year
to maintain whilst closed. This would
take into account NNDR, security, repairs and maintenance, as set out in the
options in Appendix 5, page 6 of the business case. If the property was left in this condition
permanently it would cost approximately £355,000 over the next five years. Demolition costs were estimated at approximately
£1M, and a detailed summary had been included.
In reply to questions from Members, it was
explained that the business case, Appendix 5, had been scrutinised and approved
by the SIG investment group and
they had sufficient confidence to recommend to Council that the development of
the Nova Centre proceed. Prestatyn Town Council, the Coastal Board and Prestatyn Member Area Group had been consulted throughout
the development stages. Members
expressed their appreciation regarding the depth of the consultation process
undertaken. The Equality Impact Assessment had been attached as Appendix 6.
If approved the construction cost of the
scheme would be fixed, as set out in the development partner framework. Any deviations from the agreed capital sum would
be borne by ALS, unless costs were as a consequence of any additional request
that was over and above the agreed scope of works. It was confirmed that options had been
discussed with the SIG, and on the basis of how the risk would be managed, they
had agreed to recommend for development, pending Council approval.
Councillor H.Ll. Jones
complimented the work undertaken with ALS.
He explained that the Nova Centre project would be the second of three
projects which included the recently completed Bowls Centre, Prestatyn, and the Sun Centre, Rhyl. Councillor H.H. Evans referred to the in
depth scrutiny process undertaken in progressing the project, which had
considered every possible aspect of the scheme.
He felt that Denbighshire had led the way in Wales by promoting the
provision of leisure services, which in turn could relieve pressure on the
Health Service.
Reference was made by Councillor C.H. Williams to the
possible loss of the school playing field at Ysgol Gynradd
Llandrillo.
The HCML informed Members that in terms of small villages and rural
areas benefiting from investment, the leisure strategy had been clear. He explained that due to population figures
and the difficulty of increasing commercial viability, some areas of the County
would need to be funded by areas of the service where expectations had been
exceeded.
During the ensuing
discussion the HCML provided the following responses to questions submitted,
and issues raised by Members:-
-
The Ffrith Beach Fun Park lease holder would be included in the
discussions relating to the development of the Nova Centre, and the future
development of the land between the Ffrith and the
Bowls Centre.
-
Reference
was made to the potential increase in employment in the area, and the boost to
the local economy and tourism industry across the coastal area.
-
Details
were provided regarding the construction timescales.
-
The
importance of leisure services to the Social Care Agenda was highlight
-
With
regard to the provision of a water slide at the Nova Centre, it was explained
that during the appraisal of the leisure offer and consideration of the mix of
facilities along the coastal area, it had been agreed that the fun aquatics
element in terms of leisure waters would be better located in Rhyl, with the facility in Prestatyn
focusing more on formal waters.
-
The
HCML provided details of the framework and contract with ALS. He confirmed that Denbighshire had benefited
from a professional framework of services which inform the Council of the
services available and market demands.
-
An
outline of the proposed concessions relating to the retail units was provided
by the HCML. He explained that the aim
had been to market the Nova Centre as a destination for visitors to Prestatyn and the coastal area. It was confirmed that determining the best
possible option in respect of the food and beverage offer, through the
restaurant facility, would be critical to the success of the Centre.
-
A
bilingual service had not previously been provided as the facility had been
operated by an arms-length independent company. However, future provision had
been addressed. The HCML confirmed that
where possible Welsh speaking staff would be employed, but the requirement to
appoint accredited staff did provide restrictions.
-
In
response to a request from Members, the HCML confirmed that an annual
evaluation on the progress of the Nova Centre, against the Improvement Plan set
for the Leisure Strategy, could be provided.
-
Members
were informed that it had been set within the framework of the contract that ALS
utilise local labour and suppliers where possible.
-
The
HCML provided details of the flood and storm protection measures for the
building, which included improvements to the promenade and sea defense wall.
The Chair and
Members thanked the HCML, his staff and ALS for the excellent work undertaken
in respect of the project during the limited timescales.
Following further
discussion, and on being put to the vote the recommendation in the report was
agreed:-
38
votes for and 1 abstention.
RESOLVED – that Council approves
the £4.217M refurbishment of the Prestatyn Nova
Centre.
Supporting documents:
- Nova Report, item 6. PDF 105 KB
- Nova App 1, item 6. PDF 289 KB
- Nova App 2, item 6. PDF 38 KB
- Nova App 3, item 6. PDF 86 KB
- Nova App 4, item 6. PDF 81 KB
- Nova App 5, item 6. PDF 5 MB
- Nova App 6, item 6. PDF 158 KB