Agenda item
WAO ANNUAL IMPROVEMENT REPORT - 2013/14
To consider a
report by the Head of Business, Improvement and Modernisation (copy enclosed) on
the annual assessment of the Council’s prospects for improvement, undertaken by
the Wales Audit Office.
Minutes:
A
copy of a report by the Head of Business, Improvement and Modernisation (HBIM),
on the annual assessment of the Council’s prospects for improvement undertaken
by the Wales Audit Office (WAO), had been circulated with the papers for the
meeting, together with, a copy of the WAO, 2014/15 Performance Audit work and
Fees letter.
The WAO
Representative (GB) introduced the report and explained that the Annual
Improvement Report, Appendix 1, provided information on the Councils Annual
Improvement Report (AIR). Under the
Local Government Measure, the Wales Audit Office annually reviews the Council’s
progress towards meeting its objectives and its prospects for continuing to
improve in the year ahead.
For the year
2013-14, the WAO had concluded that:-
·
Denbighshire
made good progress in delivering improvements in all its priority objectives
for 2012-13 but further improvements are required in a few key areas;
·
The
Council’s service challenge reviews and other measures to self-evaluate its
performance are robust;
·
The
Council’s planning for improvement and its arrangements to support improvement
are good;
·
The
Council is likely to make arrangements to secure continuous improvement for
2014-15.
It was explained
that if the WAO had significant concerns about the progress made by the Council
or the direction it was taking, it would make formal recommendations for
change. Denbighshire’s report did not
have any formal recommendations and this reflected the WAO’s positive view of
the Council’s progress.
Confirmation was
provided that some areas required further work and both last year’s and this
year’s Annual Reports had made some ‘proposals for improvement’. Denbighshire had made good progress with all
the proposals made in the 20012/13 report and this year the Inspectors had made
two further proposals which they considered would help the Council continue to
progress. These included:-
·
P1 - In
order to achieve its objective to modernise services the Council should
continue to address weaknesses in its Corporate Human Resource Service.
·
P2 -
The Council should ensure that roles and responsibilities are clear for the
achievement of the affordable housing objective.
The Council
accepted the proposals and taken action to address them. Denbighshire were continuing to work through
an action plan to address the identified shortfalls in the HR service, and a
Task Group was being established to review objectives in relation to the
affordable housing issue,
Reference
was made by the WAO Representative to paragraph 30 of the report which
indicated the level
of financial reserves held by schools in Denbighshire had increased
significantly during 2012/13 to £2.9m.
In response to a suggestion by Councillor M.L. Holland, the Committee
agreed the issue pertaining to school balances be referred to the Scrutiny
Chairs and Vice Chairs Group for consideration.
Councillor M.L. Holland raised issues pertaining to
the following sections in the report:-
17. The reasons for the unsuccessful bid for Welsh
Government funding from the Vibrant and Viable Places Fund to support
initiatives within Rhyl.
45. There being any pattern to the recorded
incidents of fly-tipping being higher than the average for other Councils in
Wales.
52. Registration
issues in the County in respect of affordable housing.
The WAO
Representative gave a summary of the Wales Audit Office, 2014/15 Performance
Audit Work and Fees letter, and provided responses to questions from Mr P. Whitham in respect of the WAO performance audit work
2014/15, Governance.
Members were
informed that the WAO would be liaising with the relevant officers and
subsequently reporting to Corporate Governance Committee. The work would be undertaken later in the
year and would form part of the next Annual Improvement Report.
The HIA referred to
the Audit Plan which incorporated work relating to school financial management
and this report would be presented to the Corporate Governance Committee.
During the ensuing
discussion the Chair explained that an item pertaining to Strategic Human
Resources had been included in the forward work progamme
for the 3rd September, 20124, and a Work Shop had been convened with
regard to Affordable Housing.
RESOLVED – that the Corporate
Governance Committee:-
(a)
receives
and notes the contents of the Annual Improvement Report.
(b)
receives and notes the contents of the Wales
Audit Office, 2014/15 Performance Audit Work and Fees letter, and
(c)
the
issue pertaining to school balances be referred to the Scrutiny Chairs and Vice
Chairs Group for consideration.
Supporting documents:
- WAO Ann Imp Report, item 7. PDF 50 KB
- WAO Ann Imp Rep App 1, item 7. PDF 1 MB
- WAO Ann Imp Rep App 2 (Fees Letter), item 7. PDF 174 KB