Agenda item
BUDGET PROCESS 2015/16
To receive a report from the Head of Finance and Assets
(copy enclosed) on the proposed process to deliver the revenue budget for
2015/16.
Minutes:
A
copy of a report by the Head of Finance and Assets, which provided an update on
the proposed process in the delivery of the revenue budget for 20125/16, had
been circulated previously. The
Council’s approach to setting its revenue budget had been to incrementally
reduce costs based on saving proposals from services and corporate
budgets. The majority of proposals had
been accepted and the process had delivered successful budgets.
Councillor J. Thompson-Hill
introduced the report and explained that future settlements in the Corporate
Plan had indicated that savings of approximately £12m might be required over
the next two years and a new approach to savings might be required. Appendix 1 detailed how the process might
work and further detail had been incorporated in the report. Budget saving targets would be divided into
three strands for both 2015/16 and 2016/17 and a table indicating the strands,
with approximate values, had been included in the report. The values for the first two strands could be
estimated with a degree of certainty.
The third strand would be more difficult to estimate and was currently
shown as a balancing item to achieve a target of £12m savings over the next two
years. Two services had undertaken pilot
exercises which had been extremely useful in understanding how the new process
would work. A summary of the Freedoms
and Flexibilities (F&F) process had been outlined in the report.
The output from
both the F&F and the service budget meetings would be collated and
presented initially to SLT and then to three Member
budget workshops in July, and a summary of the process had been included in the
report. Budget workshops would provide
an opportunity for wider Member input to the recommendations. Reference was made to Appendix 1 where the
options were shown emerging from the Member workshops. Proposals supported by Members would be
submitted to Council in September for approval.
It was proposed that all
budget workshops would be day events and a draft outline of the service areas
focussed upon in each of the July workshops had been included. This would complete Phase 1 of the budget
process and move into Phase 2. The same
approval and consultation process would follow with more proposals being
submitted to Council in December.
Phase 3 would be
the most difficult stage of the budget to achieve as it was likely to include
the most contentious proposals. The
outcome of the first two phases would help plan the approach to the third and
this may have to be revisited in the autumn.
Councillor
Thompson-Hill provided a detailed summary of provisional key dates which had
been indicated in a table included in the report, and he confirmed that some of
the proposals submitted could be subject to public consultation.
Mr P. Whitham suggested that consideration be afforded to project
or programme management with regard to the risk and mitigation process, which
could assist the reporting mechanism in relation to summarising key
issues. The CA outlined the process
adopted to ensure that all proposals and details were captured for
deliberation, and he provided details of the new template developed to assist
the Freedoms and Flexibility process.
Councillor S.A.
Davies emphasised the importance of Member involvement and the need for
openness and transparency in the budget process.
The following
response was provided to questions submitted and issues raised
by Councillor G.M. Kensler:-
-
Correspondence
would be circulated to Members prior to budget meetings.
-
Single
Status work had been completed. However,
elements pertaining to back pay would require finalisation.
-
There
had been minimal impact to date on the Council following the introduction of the
Bedroom Tax.
-
Issues
pertaining to Town and Area Plans would be incorporated in the budget process,
together with, Public Realm and Heritage issues.
-
Details
were provided of financial working practices in terms of Net and Gross
figures.
In reply to
concerns raised by Mr P. Whitham regarding the need
for assurances that the budget process was acceptable and compliant, it was
agreed to include in the timetable of key events the process review to be
undertaken by CET, after the first two or three F&F meetings, and the
inclusion of the provision for reporting the outcomes and progress of the
review to the Corporate Governance Committee.
The CA agreed that
details of the pilot exercises undertaken by two services could be presented to
Council Briefing, together with, copies of the template to be utilised for all
services which sets out the service budget over the functions and services it
delivers. The HLDS and HIA provided
details pertaining to the identification of the provision of Statutory Services
by the Authority and the need to focus on potential outcomes.
Councillor J.
Thompson-Hill referred to the key events programme and confirmed that it would
not be viable to repeat sessions. He
explained the onus would be on Members to attend meetings where possible or
pursue any outcomes. The Committee
agreed that details of Members invitations to attend meetings be included in
the key events programme.
Following further
discussion, it was:-
RESOLVED – that, subject
to the issues raised and comments made by Members, the Corporate Governance
Committee:-
(a)
receives and notes
the contents of the report.
(b)
agrees the
inclusion, in the timetable of key events, the process review to be undertaken
by CET, and provision for reporting the outcomes and progress of the review to
the Corporate Governance Committee.
(c)
requests that
details of the pilot exercises, and copies of the template, be presented to
Council Briefing, and
(d)
agrees that details of Members invitations to attend
meetings be included in the key events programme.
Supporting documents: