Agenda item
WASTE SERVICE REMODELLING PROJECT UPDATE
To receive an update report (enclosed) by the Waste and Recycling Manager associated with the roll-out of the new service.
11:45 – 12:15
Minutes:
The Lead Member for Highways and the Environment introduced
an update report (previously circulated) on the roll out of the new Waste
Service Remodelling Project.
The
report was to inform the Communities Scrutiny Committee of the current progress
of the project and to highlight the risk around the timely approval of the
operational permit required for the new Denbigh Waste Transfer Scheme.
The
Project’s Corporate Executive Team (CET) lead officer explained to Members that
the new Waste Service was the biggest operational change delivered by the
Council for many years and had been many years in planning to get to this
stage.
The
new service would include recycled waste being collected weekly in separated
containers and residual household waste being collected monthly.
The
main issue currently was obtaining the operational permit which required to be
granted by Natural Resources Wales (NRW), without this permit the Waste
Transfer Station could not operate. It
was expected that the permit would be granted in Spring 2024. The Council had
submitted the application form for the permit for the Denbigh Waste Transfer
Depot in January 2023 however, there had been a delay with NRW issuing permits
due to a back log. This had now been resolved, the process which was expected to
take up to 4 months to complete was now underway and weekly positive
discussions were continuing with NRW.
Any concerns raised during these meetings would be escalated immediately
to Lead Member and CET Lead Officer level.
The
new Waste Service Remodelling Service had a planned roll out from June 2024
with the depot being completed by December 2023.
Going
forward there was a focus on recruiting staff and delivering the new containers
to all households in the county.
The
Project Team would be attending all MAG meetings in February/ March 2024 to
give further detail on the roll out of the Project in their areas.
The
Chair thanked the Lead Member and the Project Executive Lead Officer for their
update and questions were welcomed from Members.
Members
stated that a recent visit to the new Denbigh waste depot was very beneficial
and requested another visit prior to the roll out of the service.
Members
queried the change to electric wagons under the new service and questioned who
was responsible for the cost of them. The Project Executive lead officer stated
that the new service required a whole new fleet of wagons to deal with the
kerbside sort containers within the new Recycling Service. However, current residual waste vehicles
would still be suitable for delivering that service as the service model was
not changing, only the frequency of service provision. Whilst more electric vehicles had been
introduced into the fleet, the fleet was not entirely electric as there was a
need to ensure robustness for all refuse collection rounds in the county.
Members
registered their concerns regarding the potential backlash of complaints from
the public that were anticipated and stated that this was not highlighted
enough within the report. The Project
Executive lead officer assured members that there was an understanding that
residents would have some concerns about the change. In the New Year (January
2024) planned communications would be rolled out 6 months before the
implementation. Other authorities who already had transitioned to the new model
Waste Recycling Service had stated that there were concerns at the start of the
roll out. However, once residents understood the new system residents preferred
it.
Members
questioned the total cost of the roll out of the project. The Project Executive
lead officer stated that the Project was costing circa £22 million. Due to the
current financial climate predicted costs had increased. £12 million of funding
had been given from Welsh Government, with the remainder of the costs being met
from within Service reserves and through Prudential Borrowing. It was stated
that the cost of running the new service, once fully operational, would be less
than the recycling service currently in place.
The
Lead Member and officers acknowledged that, at present, the greatest risk to
the timely roll-out of the new Service lay with the granting of the permit for
the Waste Transfer Station by NRW.
Although there was not a Plan ‘B’ or a contingency plan in place to
instigate if there was a delay with the permit’s granting, the Lead Member and
officers were confident given the regular discussions underway with NRW both
locally and nationally that the permit would be granted in time.
Members
stated and agreed that there was a need to be positive about the new Waste
Service and work with officers to inform the public.
The Chair thanked the Lead Members and the Project Executive lead officer for their report.
Following a detailed discussion, the Committee:
Resolved:
subject to the above observations and the answers given to the questions
raised -
(i)
to acknowledge the progress made
to date with the Project’s delivery, including the efforts made to secure the
timely approval of the operational permit required for the new Denbigh Waste
Transfer Station; and
(ii)
that as part of its consideration
it had read, understood, and taken account of the recently updated Well-being
Impact Assessment, attached at Appendix 1 to the report.
Supporting documents:
- Waste and Recycling Project Report 19102023 Communities Scrutiny, item 6. PDF 149 KB
- Appendix 1 WBIA, item 6. PDF 150 KB