Agenda item
DENBIGH INFIRMARY
- Meeting of Partnerships Scrutiny Committee, Thursday, 4 April 2019 10.00 am (Item 5.)
- View the declarations of interest for item 5.
To receive a presentation from Betsi Cadwaladr University Health Board representatives regarding future plans for the provision of services at Denbigh Infirmary.
10.10 a.m. – 10.45 a.m.
Minutes:
The Chair welcomed Betsi
Cadwaladr University Health Board’s (BCUHB) Director
of Clinical Services – Therapies and Assistant Director of Community Services
to the meeting to discuss the future provision of services at Denbigh
Infirmary. Apologies had been received
from the Area Director: Centre BCUHB (Bethan Jones).
Introducing the presentation the Health Board’s
Assistant Director of Community Services provided the Committee with a brief
overview of the background to the closure of the ward at Denbigh Infirmary,
including information on the detailed fire surveys and inspections undertaken
and their findings which had resulted in work being commissioned to establish
the costs and timescales for making the ward fit for purpose again. This work had identified eight potential
options for future re-provision of services at the Infirmary. These were the –
·
refurbishment
of the existing first and ground floor areas to re-provide 14 beds at an
estimated cost of £10m to £11m, within an anticipated timescale of 3 years
·
demolition
and rebuilding of the ground and first floor area to re-provide 16 beds at an estimated
cost of £11m to £12m, within an anticipated timescale of 3 years
·
relocation
of the Physiotherapy Department to another part of the hospital to enable the
creation of a 4 bed bay at an estimated cost of between £1.2m to £1.4m, within
an anticipated timescale of 2 years
·
construction
of a new 5 bed ward between the current MacMillan Suite and the Clinic building
at an estimated cost of between £1.2m and £1.3m, within an anticipated
timescale of 2 years
·
construction
of a new 6 bedroom ward at an estimated cost of between £4.5m and £5m, within
an anticipated timescale of 3 years
·
demolition
of the kitchen area and ward area above and the rebuilding of a 6 bed ward at
an estimated cost of between £3.5m and £4m, within an anticipated timescale of
3 years
·
conversion
of the conservatory adjacent to the MacMillan ward into a single bedroom unit
without a bathroom at an estimated cost of £100k, within an anticipated 12
month timescale
·
relocation of the
maternity room to a ground floor location at an estimated cost of between £350k
and £400k within an anticipated 12 month timescale.
Further work was currently being undertaken in
relation to the identified options.
If following detailed analysis a decision was
taken to proceed to re-provide the whole ward this would necessitate the
closure of the entire hospital site while the work was being undertaken. To ensure that there was sufficient community
beds available within the area whilst the re-provision work was underway the
work could not be commenced until such time as the new North Denbighshire
Hospital was open. Nevertheless, some
work on the site could be undertaken in the meantime. Local county councillors and the Infirmary’s
League of Friends were keen that the ward was not left empty in the meantime as
they felt that it sent out the wrong message about the site’s future, therefore
the Health Board and the County Council had recently agreed that members of the
joint health and social care Community Resources Team (CRT) for the Denbigh
area should be based at the former Lleweni Ward at
the Infirmary until any refurbishment and re-provision work was ready to be
commenced. The CRT would relocate
elsewhere when the refurbishment work was due to begin.
Members were advised by the Assistant Director
of Community Services that Health Board officials had recently met with members
of the Denbigh Member Area Group (MAG) to discuss the future of the
Infirmary. At that meeting MAG members
had asked the Health Board to consider wider options for the site in conjunction
with Denbighshire County Council and the other partner organisations. Since that meeting the Health Board had been
successful in securing some Integrated Care Fund (ICT) funding to facilitate
exploratory work in relation to mapping out a joint vision for integrated
health, well-being and social care services for the Denbigh area.
Responding to members’ questions Health Board
officials –
·
confirmed that
consideration had been given when Lleweni Ward closed
to the potential of re-providing beds on a temporary basis in specialist mobile
units. Due to the limited space available on site and the need to
continue with the delivery of other services at the hospital the re-provision
of beds in mobile units had been deemed unsuitable. If a decision was
taken to demolish and rebuild the ground and first floor wards it would
certainly be inappropriate to attempt to deliver hospital in-patient services
from mobile units on a site which would also be a construction site. In
addition hospital wards/in-patient beds would require easy access to ancillary
services, this would not be possible if they were located on a construction
site;
·
advised that they were
of the view that the Health Board would have more leverage to secure Welsh
Government (WG) capital funding for the development of the Denbigh Infirmary
site if any proposed project was a joint venture with the local authority for
the purpose of delivering integrated health, social care and well-being
services. If the proposal was only to refurbish the current premises the
Health Board would be less likely to be able to secure WG funding and would
therefore need to fund the costs from within its own budget. Discussions
were currently underway with both Denbighshire County Council and Grŵp Cynefin with a view to
developing a health and care vision for Denbigh as a basis for compiling a
robust business case to apply for WG funding. The ICF grant money would
help facilitate this exploratory work as well as work with the wider community
to determine a vision for the area and the facilities required to deliver the
vision;
·
informed the Committee that to date the Health
Board had secured grant funding for healthcare developments in Rhyl, Corwen and Prestatyn, it was now
focussing on the Denbigh area;
·
confirmed that following
the Grenfell Tower fire the WG had instructed all Health Boards to inspect all
in-patient facilities which were above single storey in height. It was
this detailed inspection, in accordance with WG instructions, which had
rendered the upstairs ward at the Infirmary unsuitable for inpatients due to
the method by which it could be evacuated in the case of an emergency. In
line with the requirements of the Fire and Rescue Services Act 2005 the
hospital did have a fire evacuation plan in place which entailed a horizontal
evacuation plan for the first floor ward. Albeit that this plan, in
recent years, had been endorsed by all fire safety inspectors, the Health
Board’s own inspectors and those employed by the Fire and Rescue Service, it
did not meet the requirements of the new guidelines published by WG post the
Grenfell Tower disaster. The Health Board was required to deliver its
services in premises which were compliant with WG safety standards;
·
advised that the first survey undertaken of the
building, during the summer of 2017, had discovered that the lack of fire compartmentation on the upstairs ward was a risk and
consequently 10 beds (2 x 5 bed bays) had been withdrawn. This survey had
concluded that the 7 remaining beds on the ward could only be used by patients
who were sufficiently mobile to walk in the event of an evacuation.
However, a further more detailed survey had rendered these beds not
sufficiently safe in the event of a fire and consequently the entire ward had
been closed for inpatient occupation;
·
confirmed that the
take-up of maternity services at the Denbigh Infirmary, when it was open, was
in the region of 10 to 12 per annum. The services available there were
similar to those available for home births. Whilst consideration could be
given to whether or not to continue with this service as part of the site’s
future development it was important to bear in mind that an educational bursary
was available for students who were born at the Infirmary;
·
advised that they were keen to work with the
local authority, Grŵp Cynefin
and the town’s four GP surgeries to develop a holistic health, social care and
well-being vision for the town with services being provided in an easily
accessible facility as well as delivered in residents’ own homes with a view to
supporting independence and building resilience;
·
confirmed that, despite it being one of the
oldest hospitals in Wales, the Infirmary was not at present a listed building:
·
advised that Health
Service Estates personnel had explored a number of potential structural
solutions that would enable the upstairs ward to re-open. The only viable
option would be for the ward’s wooden floor to be replaced with a concrete
floor. However due to the building’s age and fabric it was unlikely that
the current building’s foundations would be sufficient to support an elevated
concrete floor. Consequently, current outline proposals for the
building’s refurbishment included the erection of a steel frame as part of the
capital investment plan;
·
advised that the
community healthcare needs in the Denbigh area were different to those in the
north of the county as the demography of the local area was different.
Residents in the central part of the county were far more likely to have family
network support available to them, and
·
confirmed that whilst any
future major project to redevelop the entire site would be required to follow
the three stage WG capital projects procedure it was anticipated that in the Infirmary’s
case this process would not be as protracted a process as the one for the North
Denbighshire Community Hospital, as the vision for Denbigh was already a
collaborative one and the lessons in business case planning which had been
learnt from the North Denbighshire project should aid the development of the
business case for Denbigh.
The Council’s Head of Community Support
Services advised that the local authority was acutely aware that there would be
a growing need in the area in future for elements of nursing care as well as
specialist dementia care – both at home and in a residential/nursing home
setting. The Council was therefore keen
to work with the Health Board and partners in order to secure fit for purpose
services for residents for the future.
At the conclusion of the discussion the Committee –
RESOLVED to –
(a) receive
the information and presentation on the work undertaken to date in relation to
the future provision of services at Denbigh Infirmary;
(b) support
the efforts underway to develop a health, social care and well-being vision for
the Denbigh area, and
(c) request
that the Committee be updated on the progress made with developing the vision
and business cases to realise it.