Agenda item
DELIVERY OF BAND B - 21ST CENTURY SCHOOLS PROGRAMME
- Meeting of Cabinet, Tuesday, 23 January 2018 10.00 am (Item 6.)
- View the declarations of interest for item 6.
To consider a report by Councillor Huw Hilditch-Roberts, Lead Member for Education, Children and Young People (copy enclosed) on progress in respect of Band B of the 21st Century Schools Education Programme and the implications for delivery.
Decision:
RESOLVED that Cabinet –
(a) confirms its financial commitment to
delivering Band B proposals in accordance with the Strategic Outline Programme
as submitted to the Welsh Government to enable it to meet the priority included
within the Corporate Plan 2017 – 2022, and
(b) confirms that it has read, understood and
taken account of the Well-being Impact Assessment attached at Appendix 1 to the
report as part of its consideration.
Minutes:
Councillor
Huw Hilditch-Roberts presented the report advising Cabinet of the approval of
its Band B programme submission for the 21st Century Schools and Education
Programme and the implications for delivery.
The
Council had made excellent progress in delivering the Band A
proposals in partnership with Welsh Government and together would have invested
over £90m by 2019 to deliver key projects.
In July 2017 Cabinet approved submission of Band B proposals worth £80.5m
to Welsh Government as part of the next phase of investment. Welsh Government had since approved the
investment in principle subject to approval of individual project business
cases. Consequently Cabinet was asked to
confirm the Council’s financial commitment to delivering Band B proposals in
line with the Corporate Plan.
Denbighshire’s contribution would be £32.8m and the revenue budget
required to fund the borrowing to support the programme would be approximately
£1.8m over the seven years of the programme.
No detail had been provided in terms of individual proposals which would
be subject to individual business cases being considered by the Strategic
Investment Group and Cabinet.
Cabinet
welcomed the report and investment in school building works for the benefit of
children and young people and the Leader was keen to continue the investment
and progress of the previous Council and take advantage of any available
funding from Welsh Government for that purpose.
Councillor Mark Young highlighted the need to ensure an open process for
communities and the Lead Member provided assurances with regard to lessons
learnt from previous reviews which would be reflected in future processes.
The
Lead Member and Head of Education and Children’s Services responded to
questions from non-Cabinet members as follows –
·
the
Strategic Outline Programme had been submitted prior to the recent announcement
of additional monies specifically for Welsh Medium education. However members were reminded that
approximately £30m had been invested in increasing and improving facilities for
Welsh Medium education in the Band A tranche of
funding and further assurances were provided that any plans taken forward in
Band B would focus on continuing to strengthen and increase provision for Welsh
Medium education. Officers were keen to
ensure members were informed of any announcements from Welsh Government which
may add to or enable plans to be taken forward to invest in the school estate
generally
·
officers were committed to ensuring that any
deficits in educational provision across all schools in Denbighshire were
addressed and the provision for ASD Learners had been debated during
development of the Strategic Outline Plan; that debate would continue as more
detailed plans were developed
·
once Cabinet had confirmed its financial
commitment it would be possible to undertake extensive discussions around any
subsequent proposals brought forward in line with the democratic process and
adherence to the School Organisation Code policies and procedures
·
assurances
were also provided that officers worked closely with design teams regarding
environment impacts and recognised the commitment to ensure environmental
demands were met as far as possible within the financial resources available for
particular projects.
RESOLVED that Cabinet –
(a) confirms its financial commitment to
delivering Band B proposals in accordance with the Strategic Outline Programme
as submitted to the Welsh Government to enable it to meet the priority included
within the Corporate Plan 2017 – 2022, and
(b) confirms that it
has read, understood and taken account of the Well-being Impact Assessment
attached at Appendix 1 to the report as part of its consideration.