CONTAINER PROCUREMENT FOR WASTE REMODELLING PROJECT

The decision relates to the procurement of dry recycling containers (Trollibocs) to support the new waste model (kerbside sort). The decision enables a direct award of contract to the supplier following a PIN Notice exercise in March 2022.

 

Decision type: Non-key

Decision status: Recommendations Approved

Notice of proposed decision first published: 22/09/2022

Decision due: 22 Oct 2022 by Lead Member for Environment and Transport

Lead member: Lead Member for Environment and Transport

Consultees

The Project Board, chaired by the Corporate Director – Environment and Economy (who acts as the Project Executive) meets approximately monthly and at each Project Board updates on risk and the latest position costs are presented for review and action as required.

 

The overall principle of moving to a new waste delivery model, inclusive of delivery of new kerbside sort recycling containers, was originally approved at SIG and Cabinet in December 2018 and subsequent updates have been presented at Communities Scrutiny in October 2019 and May 20221 and Cabinet Briefing in March 2021. 

 

Decisions