Issue - decisions
Issue - decisions
PHASE 2 SOCIAL HOUSING RETROFIT WORKS - RHYDWEN DRIVE, RHYL
03/10/2022 - PHASE 2 SOCIAL HOUSING RETROFIT WORKS - RHYDWEN DRIVE, RHYL
RESOLVED that Cabinet –
(a) directly award the
contract to the contractor currently undertaking Phase 1 of the works based on
the competitive rates via the Welsh Procurement Alliance Energy Framework as
agreed by Procurement, and
(b) that the 5-day call in
period requirement prior to implementing the Cabinet decision is waived on the
basis that the current contract ends on 30 September 2022 and any delay in
contract award will lead to additional costs and programme delays leading to
the risk of missing grant stipulated spending deadlines.