Agenda item
APPLICATION NO. 23/2014/1440/PF - CLOCAENOG FOREST, SARON, DENBIGH
- Meeting of Planning Committee, Wednesday, 15 July 2015 9.30 am (Item 7.)
- View the declarations of interest for item 7.
To consider an application for erection of a 132kV electrical substation and associated works at Clocaenog Forest, Saron, Denbigh (copy attached).
Minutes:
[Councillor Meirick Davies declared a personal interest in
this item as he was a member of ‘Pylon the Pressure Group’]
An application was submitted for erection of a 132kV electrical substation and association works at Clocaenog Forest, Saron, Denbigh.
Public Speakers –
Mr. M. Barlow (Against) – disputed the need for a substation at this time and
highlighted concerns over the landscape and visual impact.
Ms. C. Duffy, SP Manweb
(For) – explained the extent of
consultation undertaken together with mitigation measures to address issues
raised. She concurred with the
conclusions of the planning report and accepted the proposed conditions.
General Debate – Councillor Joe Welch (Local Member) opposed
the application and raised concerns regarding –
·
the piece
meal approach taken to the North Wales Windfarms Project and the cumulative
effects of the substation combined with other elements of the project
·
argued
against the need for a substation at this stage given that the application for
the overhead lines project had yet to be approved; the Clocaenog
Windfarm being subject to judicial review; and other consented windfarms having
yet to be built – consequently the application was considered premature
·
lack of
public consultation and documents provided in the Welsh Language and misleading information which detracted from
the true impact of the substation
·
adequacy
of the Environmental Report and cumulative noise assessment
·
the impact and
effects on visual amenity, tourism, residents’ health and noise.
The Planning Officer (DS) responded to the
issues raised as follows –
·
the nature
of the planning application process in Wales did not allow for all elements of
the windfarm project to be dealt with under one application
·
the
applicant had advised that the substation was not dependent on the outcome of
either the Clocaenog Windfarm legal challenge or the
proposed overhead lines project and the substation would still be required
should the grid connection be via an underground cable
·
the use of
Welsh in consultations was encouraged but it was not a legal requirement
·
officers
considered the application acceptable in principle having assessed the impact
of the substation on the local area and taking into account the site was within
the Clocaenog Forest Strategic Search Area (SSA)
[planning policy stated landscape change from windfarm development was
acceptable within SSAs]
·
officers
largely agreed with the findings of the environmental report believing issues
could be mitigated
·
whilst the Public
Protection Officer had not agreed with all the calculations applied in the
cumulative noise assessment he had not challenged its robustness and had
accepted its conclusions; noise levels could be controlled via conditions in
order to safeguard local residents’ amenity.
During a detailed debate members considered the
merits of the application and expressed reservations regarding the validity of the
cumulative noise assessment’s conclusions given that questions had been raised
over the methodology used in calculating noise levels. Concerns were also raised over visual amenity
and impact on the landscape, particularly the proposed 9 metre high gantry
which would likely be highly visible, and the subsequent effects on both the
community and tourism.
Proposal – Councillor Joe Welch proposed, seconded by
Councillor Huw Williams, that
the application be refused, contrary to officer recommendation, on the grounds
of the potential cumulative noise impact and potential visual impact on the
landscape from the substation.
VOTE:
GRANT – 3
REFUSE – 20
ABSTAIN – 0
RESOLVED that permission be REFUSED, contrary to officer recommendation on the grounds of the potential
cumulative noise impact and potential visual impact on the landscape from the
substation.
At this juncture (11.15 a.m.) the meeting adjourned for a refreshment break.
Supporting documents:
- ITEM 9 - CLOCAENOG FOREST, SARON, item 7. PDF 6 KB
- ITEM 9 - CLOCAENOG FOREST, SARON - APPENDIX, item 7. PDF 864 KB