Agenda item
URGENT AND EMERGENCY CARE: FLOW OUT OUT HOSPITAL - NORTH WALES REGION
- Meeting of Partnerships Scrutiny Committee, Thursday, 3 April 2025 10.00 am (Item 5.)
- View the declarations of interest for item 5.
Minutes:
The Lead Member for
Health and Social Care and the Corporate Director: Social Services &
Education (CDSSE), alongside the Acting Assistant Director – Care Homes Support
and Continuing Health Care Commissioning and Director of Public Health (BCUHB),
presented the Urgent and Emergency Care: Flow out of Hospital – North Wales
Region report (previously circulated).The aim of the report was to provide an
updated account/information to partners regarding the associated work
undertaken since the first publication of the Audit Wales report and combined
organisational response in September 2024.
The Committee were
informed that overall, it was found that whilst partners understood and showed
a commitment to improving patient flow out of the hospital, performance
remained extremely challenging with adverse effects on patient experience and
care. Partners continued to work both individually and collaboratively to set
and implement clear guidance, mitigate the challenges posed by reduced capacity
and increased complexity of care, and ensure the impact of activities was
continually monitored, challenged, and maximised.
The original report
found that the extent of discharge delays in North Wales had grown
significantly in recent years. Between April 2023 and February 2024, each
month, there were, on average, 334 medically fit patients whose discharge was
delayed, with completion of assessments the leading cause for delay. For the
year up to and including February 2024, the total number of bed days lost to
delayed discharges was 71,871, with a full-year cost equivalent of £39.202
million. The consequent impact on patient flow within hospitals and the urgent
and emergency care system was significant, with waiting times in emergency
departments and ambulance handovers falling well short of national targets. In
February 2024, there were over 8,000 lost ambulance hours because of handover
delays, and the average wait within the Health Board’s emergency departments
was around 8.5 hours. Difficulties with discharge also impacted the ability of
partner organisations to meet some patients' needs effectively, especially in
the west of the region, where a significant proportion of patients were placed
in temporary accommodation post-hospital discharge.
Members drew
attention to several areas within the report and discussed the following
further –
- whether the
continual negative press/media coverage received by the Health Board
contributed to the difficulties encountered in recruiting staff at all
levels, thus impacting the flow in and out of the hospital. Officers responded that negative press
coverage was an issue. However, it had no impact on staffing, and the
staffing levels were acceptable in all disciplines other than mental
health, which was still proving challenging to hire staff.
- the steps being taken
to ensure that vulnerable patients were not discharged home in the middle
of the night with no one to receive them when they arrived. What support
was made available to them to make sure they fully understood when and how
to take their medication etc and whether any follow-up visits were
scheduled. Responding officers acknowledged there were issues with the
discharge process and agreed with members that vulnerable people should
not be discharged in the middle of the night. BCUHB officers emphasised that
vulnerable patients should not be discharged in the middle of the night
and without support. If this was
happening it should be reported as an incident. The Health Board held hourly discharge
data, which was closely monitored, and worked closely with the community
health team to ensure follow-ups were being carried out.
- The Health Board had
recently finalised its hospital discharge policy win cooperation with the
local authority and other stakeholders.
- whether
communication channels were sufficiently effective to ensure that patients
deemed medically fit for discharge were provided with proper support to
aid their discharge. Officers clarified that a lot of work and
communication was carried out with patients on discharge. They were provided with leaflets
containing all relevant information and contact details. There was ongoing work to improve the
information sharing between organisations and improving communication
throughout. Further work was being undertaken in a bid to streamline the
discharge process through the introduction of an electronic process. In addition, Optimal Flow Facilitators
had now been employed with a view to improving patient flow in and out of
hospital. At present all three
Optimal Flow Facilitators were focussing their work at improving the flow
in and out of Ysbyty Glan Clwyd.
Regarding support and carers, officers clarified that they strived
to provide local care for residents, and the use of micro providers
assisted with this.
- the Regional
Integration Fund (RIF) monies and queried whether officers believed the
funding would continue beyond 2027.
Officers informed the Committee that they were continuously
discussing the RIF monies and potential funding post-2027 with the Welsh
Government (WG).
- the report was a
regional overview and was not solely focused on Denbighshire. Its findings and recommendations along
with the progress in delivering the identified actions were discussed at
the North Wales Regional Partnership Board (NWRPB). It had initially been presented to the
Governance and Audit Committee which suggested the report be brought to
scrutiny. The delay in its
presentation to Scrutiny was due to the democratic process of the report
being sighted by the relevant bodies before being discussed at the current
meeting.
- ‘RIF slippage
monies’ would accrue when a role was vacant and had not been filled for
some time. Whilst the post was
vacant the funding would be reallocated where required.
- Officers clarified
that each organisation on the NWRPB contributed towards the work of
delivering the action plan.
- With regards to
delayed discharges Members were advised that these usually entailed
complex needs which required multidisciplinary team meetings to fully
assess the individual’s care needs.
Delay codes
were being reviewed nationwide with a view to simplifying
the procedure.
- A member of the
Single Point of Access (SPoA) team was now
located at the hospital with a view to co-ordinating service enquiries
more effectively.
- With regards to
sickness absence levels officers reassured members that there had been a
slight increase in sickness absences.
However, when working in health or social care, unlike other
sectors, people could not work when suffering with sickness bugs, colds
etc. due to the risk of passing them on to vulnerable clients, this caused
short-term illness statistics to increase.
- Members raised
concerns about the lack of local knowledge from secondary care providers,
as many agency workers did not know the local area and could not locate
people appropriately. Other concerns were the IT systems used by the
health and social care sector the perceived lack of synergy between
them. Officers advised that there
were ongoing meetings with WG, which aimed to focus more on
community-based care, and there was ongoing work to get the IT systems
working better together.
- Confirmation was provided that work was underway to streamline pharmacy
services in a bid to improve the discharge process.
- Officers confirmed
that partnership working arrangements were strong and positive, neither
partner was blaming each other. It
was the media that was attempting to create divisions. The NWRPB was working to improve the
service provided regionally, with cooperation and joint working. This approach at times required some
compromises, but it was realising its objectives.
- Advised that in order to enable residents to live fulfilling lives
there was a need to reframe the narrative and move the focus from a
hospital centric system to a community care one. This required a shift to a preventative
and early intervention approach in primary and community care.
- Confirmation was
provided that regular maintenance plans were in place for critical and
specialist equipment at the hospitals.
- The Committee agreed
that it would be prudent to have a follow-up information report on the
action plan as soon as possible.
At the conclusion of a comprehensive discussion the
Committee:
Resolved:
(i)
to confirm that it had read,
understood and taken into account the work that was required on a continual
basis to meet the expectations and improve hospital flow in North Wales;
(ii) that
the Lead Member and officers take note of the Committee’s observations on the
work undertaken to date through the North Wales Regional Partnership Board to
address the recommendations; and
(iii)
that a further Information Report
on the progress made in delivering the combined organisational action plan in
response to the Audit Wales recommendations be circulated to Committee members
when available.
At this juncture the Committee adjourned for a comfort
break at 12.55pm and reconvened at 1pm.
Supporting documents:
-
Flow Out of Hospital Scrutiny Report 030425, item 5.
PDF 242 KB
-
Flow Out of Hospital Scrutiny Report 030425 - App 1, item 5.
PDF 560 KB
-
Flow Out of Hospital Scrutiny Report 030425 - App 2, item 5.
PDF 397 KB