Agenda item
ROYAL ALEXANDRA HOSPITAL (RAH) DEVELOPMENT
- Meeting of Partnerships Scrutiny Committee, Thursday, 13 February 2025 10.00 am (Item 5.)
- View the declarations of interest for item 5.
To consider a report by the Programme Manager from Betsi Cadwaladr University Health Board (copy attached) which updates the Committee on progress and plans for the development of the Royal Alexandra Hospital site and seek members’ feedback on the proposals.
10:10am – 11:00am
Minutes:
The Lead Member for
Health and Social Care and the Corporate Director: Social Services &
Education (CDSSE) presented the Royal Alexandra Hospital (RAH) Development
report (previously circulated) alongside Betsi Cadwaladr University Health
Board (BCUHB) Integrated Health
Community Director for Conwy & Denbighshire, Gareth Evans. The report shared progress and plans for the development
of the RAH site in Rhyl.
It was emphasised
that whilst the RAH project was led by the Health Board the Council was working
very closely with Health Service colleagues on the project, with the Lead
Member and Corporate Director dedicating some considerable time and effort into
realising the development. The proposal
was to deliver new services alongside relocated and expanded supporting
services from a new clinical building. The project would also aim to refurbish
the existing RAH building as a support centre with some clinical,
patient-facing services remaining in situ, e.g., Child & Adolescent Mental
Health Services (CAMHS) and Physiotherapy.
The BCUHB Integrated Health Community Director guided the Committee through a presentation
highlighting the background and summary of the work undertaken to date on the
RAH project, including its scope, key dates, programme governance structure,
and collaborative working opportunities.
BCUHB aspired to
develop the site, which had a long history.
Whilst a business case had been submitted in 2021 but, due to
inflationary costs caused by factors outside of the control of the Health
Board, such as the pandemic and geo-political matters, insufficient capital was
available to fund the scale of work outlined in that business case.
Consequently, an Option Appraisal for a lower-cost development was agreed upon
with the Welsh Government in July 2024. It was then agreed to progress the
scope through innovative procurement of design, detailed in an Addendum to the
2021 full business case (FBC), which was submitted to WG.
Due to financial
constraints, the scope of the work had to be re-evaluated. This entailed a
design which prioritised the delivery of new services in a new, smaller
clinical building. The project also required the Health Board to prioritise the
refurbishment of the existing Grade II Listed RAH building as a support centre.
In addition, with a view to alleviating pressures at Ysbyty Glan Clwyd (YGC)
and support the local population, the Health Board was expected to provide the
following services in the new building:
·
A new
Minor Injuries and Ailments unit
·
Some
“Care Closer to Home” beds
·
Increased
opportunities for collaborative working with partners at the site
Under the revised
plans the new clinical building would accommodate the following:
·
A new
Minor Injuries and Minor Ailments Unit (MIAU) taking demand away from Ysbyty
Glan Clwyd and serving people closer to home
·
approximately
14 community beds (number subject to design constraints), which would enable
Health and Social care to meet the needs of local people
·
A
relocated and expanded Radiology service and an expanded Community dental
service.
The existing building
would be refurbished to include:
·
repairs
to the floor structure and external fabric
·
refurbishment
of current unoccupied areas
·
new
electrical and heating infrastructure
·
co-location
of the Third Sector adjacent to the Community Team; and
·
the potential
repatriation and expansion of sexual health, audiology, and orthotics services
(subject to design and funding limits).
The Committee were
advised of the indicative key dates for the project’s development and
delivery –
·
Jan
– April 2025: Procurement
(this phase was currently in progress)
·
March
- August 2025 –
submission of planning application for the site
·
May
2025: Approval by
BCUHBoard of new build design, then submission to Welsh Government (WG)
·
July
2025: Approval by
BCUHBoard for existing building, then submission to WG
·
August
2025: design and
cost update for the existing building (RIBA 3)
·
Quarter
1 2026: commencement
of the new build phase
·
Quarter
2 2026: commencement of the
work on existing building construction
The Committee were
also informed of the ongoing stakeholder engagement taking place.
·
Continual
“Bite Sized Health” engagement events
·
Rhyl
White Rose Centre events in 2025
·
Developing
the work on the wider economic benefits to the community with stakeholders in
local government and the Voluntary Sector
·
Continuation
of staff engagement events
·
Return
to the Equalities Stakeholder Group
·
A
Clinical Reference Group had recently been established.
Following the
introduction, in response to members’ questions, the Lead Member, Council, and
BCUHB officers:
·
confirmed
that the new designs were being finalised, once they were finished, planning
permission would be sought.
·
Advised
that there had been good, positive dialogue with Welsh Government (WG) and the
other local stakeholders on the project and its funding. The North Wales Regional Partnership Board
(NWRPB) had endorsed the partnership element of the funding and included it within
their 10-year Capital Investment Plan.
Health Board officials and relevant Denbighshire County Council (DCC)
officers had been involved in discussions with WG ministers at the highest
level with respect of the project.
·
The
proposed14 beds were intended to prevent people from needing to attend the
acute hospital. They were very much
viewed as a step up/step down provision which would be a key feature of future
health and social care provision, complementing other aspects of the prevention
work e.g. Community Resource Team (CRT) and other community-based
services.
·
clarified
that approximately 20% of funding within the project would come from regional
partners, via the NWRPB. The remainder
would be sourced from WG via capital funding streams.
·
Advised
that whilst car parking facilities were yet to be finalised, all partners were
confident that satisfactory solutions would be included in the final plans.
·
Confirmed
that the wards closed in 2012 were closed on fire safety grounds which would be
too costly to upgrade to meet modern-day standards.
A number of committee members expressed the
view that there was a need to reinstate community hospitals as the needs within
the community were continuously increasing and causing severe pressures on
acute hospitals, such as YGC.
The committee emphasised that the length of
time the process to redevelop the hospital was taking was frustrating,
especially for local members who had been elected members since the inception
of the proposal for the RAH development.
The Lead Member for Health and Social Care advised that she understood
members' frustrations on the matter.
However, the project had been re-scoped to accommodate budget
constraints, more capital funding had recently been promised by UK Government
to the WG for health projects therefore there was every reason to feel more
optimistic about this particular project and be forward thinking for the
future.
BCUHB Integrated Health Community Director responded to members’ concerns that the matter may fall foul of political
processes ahead of the 2026 Senedd election, stating that the project had been
ongoing through multiple electoral cycles. The WG had shown its commitment to
the project by setting aside funding for it, subject to the conclusion of the
scoping and design planning stages. It
was earmarked as one of its major capital investment projects. The project, once completed, would reap huge
benefits for the local community.
The Chair thanked
BCUHB’s Integrated Health Community Director for Conwy and Denbighshire for
attending the meeting and giving the presentation, and in conjunction with the
Lead Member for Health & Social Care and the Corporate Director of Social
Services & Education, for answering members' questions.
After an in-depth
discussion, the Committee:
Resolved:
-
(i)
to note the scope of the work, the
timescale, and potential available funding for the purpose of developing the
Royal Alexandra Hospital;
(ii) that
the feedback and observations provided during the discussion be considered as
part of the service provision planning for the development; and
(iii)
that a further progress report on
the Royal Alexandra Hospital Development be presented to the Committee at its
September 2025 meeting.
Supporting documents: