Agenda item
CORPORATE RISK REGISTER
To consider a report on the Corporate Risk Register from the Strategic Planning and Performance Officer reviewing the risks facing the Council and the Council’s risk appetite statement (copy enclosed).
10:10am – 11:00am
Minutes:
The Lead Member for
Corporate Strategy, Policy, and Equalities alongside the Head of Corporate
Support: Performance, Digital and Assets, and the Insight, Strategy and
Delivery Manager presented the Corporate Risk Review, September 2024 report
(previously circulated).
The report was an
update on the September 2024 review of the Corporate Risk Register and the
Council’s Risk Appetite Statement. It also informed the Committee of the
amended risk appetite statement regarding project financing which attempted to
reflect the present financial environment.
Therefore, it was suggested that it would be appropriate to amend the
Council’s ‘cautious’ risk appetite in relation to project financing to ‘open’.
The Corporate Risk
Register was developed and owned by the Senior Leadership Team (SLT) alongside
the Cabinet. It was reviewed twice yearly by the Cabinet at Cabinet Briefing.
Following the February and September reviews, the revised register was
presented to the Performance Scrutiny Committee and the Governance & Audit
Committee. A summary of reviews was shared for information only to both
committees ahead of their January and July meetings.
The Council
currently had 13 Corporate Risks on the Register. Summaries of the conclusions
following the latest review for this period were provided at the start of each
risk in Appendix 2. No risks had been de-escalated during this review. However,
a new risk, risk 53 (the risk that Transformational Programmes and Major
Project benefits are not fully realised), was proposed to be added to the
Register. This proposed addition would increase the total number of Corporate
Risks on the Register to 14 risks.
Regarding the risk
appetite, officers clarified that seven risks, 01, 21, 34, 45, 50, 51 and 52
(54%), were currently inconsistent with the Council’s Risk Appetite Statement
(appendix 3). Nevertheless, this was expected as the register contained the
Council’s most serious risks. Officers stated that it was timely for the
Authority to review the Council’s Risk Appetite Statement (appendix 3), which
was last revised in April 2024, as the statement needed to reflect its appetite
now reflecting on the key external factors (Political, Economic, Sociological,
Technological, Legal and Environmental) that influence an organisation along
with internal dynamics and demands. An initial discussion had taken place at
the Budget and Transformation Board in July 2024 and at the Corporate Executive
Team (CET) in October 2024
to provide feedback on the appropriateness of the Risk Appetite
Statement as it stood at that time.
The Committee was
also informed that discussions at the Budget and Transformation Board and CET
drew particular attention to the Council’s cautious risk appetite regarding
financial projects. As a result, it was proposed to move this risk appetite to
“open” to provide a more appropriate framework to support the organisation's
transformation to achieve financial sustainability and creative responses to
residents' requirements.
Following the
comprehensive introduction by officers, members discussed the following further
–
- The committee
queried the newly proposed risk, risk 53; Transformational Projects – the
timeline for the transformational programmes or major projects to
commence, be delivered, and the benefits realised, and when would they be
presented to Scrutiny? Officers clarified that any capital projects would
need to be discussed with the Capital Scrutiny Group and the Budget and
Transformation Board (BAT) before the business cases would be sufficiently
developed to be consulted upon with members. Performance Scrutiny Committee has been
allocated the committee to consider transformational projects which formed
part of the ‘Influencing Demand and Digital’ Workstream of the
Transformation Programme with scrutiny proposal forms completed for
scrutiny chairs and vice chairs consideration as business case development
progresses and projects go for approval and into delivery Once
transformation projects had been approved their delivery, along with the
benefits realised on implementation, would be regularly monitored via a
suite of key performance indicators (KPIs). Officers were advised to submit the
scrutiny proposal forms early as the Committee’s work programme was
already nearing capacity for the forthcoming calendar year.
- Whether the Council
had been too late in identifying new risk 53 and adding the risks
associated with transformation to the Register. Should this have been done
earlier? Responding officers clarified that projects had been monitored
for risks for a long time as all projects had a project risk register
attached to them, these captured the risks at a project level. However,
there was now a collective view that a new risk should be included on the
Corporate Risk Register in order to highlight the
risk posed to the Authority in general in relation to business
transformation projects and the need to get them right. Whilst the pace of travel in relation to
the projects was currently slow, it was increasing and therefore it was
important that the sufficient regard and mitigation measures were put in
place to monitor and manage the risks associated with them. National
statistics and information would in the near future
be used to when assessing and monitoring the risks associated with service
transformation projects.
- Members queried
whether the Council was too reliant on Reporting of Incidents, Diseases
and Dangerous Occurrences Regulations (RIDDOR) statistics when determining
Risk 11 relating to ‘unexpected or unplanned event occurring’. Should the Council, for example, be
using more data and evidence produced by the Emergency Planning
Service? Officers confirmed that
this needed to be strengthened, but regional, Wales and UK-wide data was
used when assessing this particular risk.
Officers were due to meet with representatives from the North Wales
Counties – Regional Emergency Planning Service (NWC-REPS) in the near future to discuss risk management in
relation to unexpected or unplanned events.
- As risk scores did
not seem to change or improve it was queried whether there was a statutory
requirement for Scrutiny to consider the Corporate Risk Register on an
annual or 6-monthly basis and if the Authority was permitted to compare
itself against other local authorities in Wales or the UK? Officers
confirmed that the Committee was not required to consider the risk
register. However, identification
of risks and their management was a key pillar of good governance and
covered by legislation. The Governance and Audit Committee (GAC) had a
statutory role to perform in ensuring the Council had appropriate risk
measures in place, whilst Scrutiny’s role was to examine the Authority’s
performance in managing all identified risks. It was therefore advisable that
performance in managing risks was scrutinised on a regular basis as the
Register was an integral document which formed a key part of assessing the
Authority's corporate health. The objective of scrutinising the Register
was to give members and officers assurances that all corporate risks were
being effectively monitored. Making the document more visually appealing
was difficult as all documents were required to be accessible to allow all
citizens to be able to read or receive the information. Officers agreed to
explore options for providing comparative data. However, this may be difficult as
different authorities had different metrics of scoring risks and KPIs.
- Risk 34 relating to
‘insufficient regulated care’— members enquired on whether the Council had
confidence that sufficient controls were in place to manage this risk
going forward? This risk continued to be a cause of concern. While it was being managed demand for
care was continuing to rise whilst resources to provide the level of care
required were proving difficult to source. This was a national problem and
Scrutiny may wish to examine it in detail, including the costs of
employing agency staff, by inviting representatives from Social Services
to a future meeting to discuss the matter.
With respect of staffing concerns and what steps were being taken
to address recruitment and retention problems in Children and Adults’
Social Care and other services across the Council, members were advised
that the issues of recruitment were a broad issue not unique in
Denbighshire. All departments and
services were working alongside HR to get a detailed picture of the
situation and the matter was due to be discussed thoroughly at March’s
meeting during the Recruitment, Retention & Workforce Planning item.
- Risk 50 – WG’s
commitment to eliminate profit from the care of Children Looked After,
which could result in an unstable or unsuitable supply of placements and
the mitigating actions being taken in an attempt to
address this risk. Members were
advised that recruitment and effective staff retention in a what was a
very competitive market was key. The Committee was reassured that the Head
of Children's Service was assessing the matter thoroughly and was studying
all the information as it became available. It was difficult to provide
definitive answers at present as the matter was continuously changing and
developing. The latest information
available indicated that both Welsh and UK Governments were currently
considering delaying the implementation of the new legislation relating to
eliminating profit from this sector until 2030. Members may therefore wish to consider
including the risk as a topic for inclusion on a Scrutiny forward work
programme for a future meeting, vis the completion of a Scrutiny proposal
form.
At the conclusion
of a comprehensive discussion, the Committee:
Resolved:
subject to the above observations and the provision of the requested
information –
(i)
having considered and discussed the suggested amendments to the
Corporate Risk Register as at September 2024, to
confirm the amendments made including the inclusion of new risk number 53 as
detailed in Appendix 4 to the report;
(ii) having regard to the status and risk
appetite classifications and descriptions detailed in Appendix 3, along with
the answers provided to the questions raised during the meeting, to confirm the
appropriateness of the risk owners identified and the effectiveness of the risk
controls put in place; and
(iii)
acknowledging the present financial environment within which public
services operated and having taken into account the
Budget and Transformation Board (BAT) and the Corporate Executive Team’s (CET)
rationale with respect of amending the Authority’s risk appetite in relation to
financial projects, to support the recommendation to amend the risk appetite
categorisation for financial projects from ‘cautious’ to ‘open’.
Supporting documents:
-
Corporate Risk Register Review Report 281124, item 5.
PDF 244 KB
-
Corporate Risk Register Review Report 281124 - App 1, item 5.
PDF 705 KB
-
Corporate Risk Register Review Report 281124 - App 2, item 5.
PDF 829 KB
-
Corporate Risk Register Review Report 281124 - App 3, item 5.
PDF 217 KB
-
Corporate Risk Register Review Report 281124 - App 4, item 5.
PDF 452 KB