ADDITIONAL RESOURCES REQUIRED FOR THE NEW WEEKLY TROLLIBOCS RECYCLING SERVICE AND ASSOCIATED WASTE COLLECTION FUNCTIONS
To consider a joint report by the Corporate Director: Environment and Economy & Head of Highways & Environmental Services (copy enclosed) to enable the Committee to scrutinise the proposal that was presented to Cabinet on 1st October 2024.
Minutes:
The Lead Member for Environment and Transport, alongside the
Corporate Director of Economy and Environment and the Head of Highways and
Environmental Services, presented the report (previously circulated). The
report detailed the implementation of the new weekly trollibocs
recycling service and associated waste collection functions
and the adjustments required to ensure sufficient resources were allocated to
ensure the new system could operate on a sustainable footing going forward and
enable the Committee to scrutinise the proposal (appended to this report) that
was presented to Cabinet on 1 October 2024.
Opening the discussion the Chair questioned whether there
had been any additional information since the Cabinet meeting on October 1, in order to prevent repetition of the previous debate.
The Lead Member and officers clarified that further to
Cabinet meeting in October the extra funding approved allowed the matter of
missed collections to be addressed.
The Corporate Director reminded the Committee that upon
introduction of the new service many rounds were failing to be completed and temporary additional resources were needed in
terms of overtime, additional agency staff and vehicles.
The majority of residents were now
getting the weekly recycling collection service although it was acknowledged
that there were still issues with some specific properties not getting a
consistent collection service.
The crux of the matter was that there was
not enough rounds designed into the service to collect from 46000 properties
across the county every week. The under resource of the service at the outset
led to the service failure. Moving forward plans had been made to deliver a
more sustainable service for the long term with the provision of additional
vehicles and drivers.
Since the Cabinet decision Welsh Government had been
approached to request additional support towards the capital spend. Welsh
Government had indicated that they were willing to provide additional support –
although the exact figure was as yet unknown. As a result the cost of purchasing the additional vehicles should
be less than previously anticipated and two of those vehicles would be electric
rather than diesel.
The service had started to implement the decision made by
Cabinet with the procurement of vehicles – six of the eight vehicles had been
ordered with anticipation of ordering the electric vehicles imminently.
Recruitment for the staff was also underway. The new reorganised recycling
rounds would commence on Monday 4th November 2024
Members had been invited to visit the Waste Station earlier
in the week to review the revised recycling rounds and check that areas that
had previously had problems were included. They were confident that normal
service would be resumed.
Whilst the Committee welcomed the update regarding the
sourcing of additional vehicles and staff they felt that it would be beneficial
to bring a
report back in spring 2025 to review how the revised rounds had influenced the
service.
Responding to members questions the officers advised:
·
Delivery of the diesel vehicles was anticipated
in December but the ULEV vehicles were due in the new
year, temporary arrangements were being implemented to cover that time frame.
·
Recruitment of additional staff was due to begin
the following week. There had been a high level of interest from the agency
staff who had been covering the rounds so far.
·
Any future missed collections should be logged
through the C360 system.
·
Collection round numbers varies
day to day, the maximum number of rounds on any given day would be 28.
·
The number of hire vehicles had been reduced
once the back log of collections had been addressed, but a few were still being
used until the new vehicles arrived.
·
The rounds were being revised before receipt of
the new vehicles to increase the efficiency of the service.
·
Systems were now in place to pull through LPG
data to include new build developments into the rounds.
·
Consideration would be given to formalising a
process around Absorbent Hygiene Product collections and urgent new
subscribers, the service were able to be flexible
under such circumstances.
·
There had been substantial work with the In Cab
technology provider regarding assisted collections prior to the roll out of the
new rounds.
·
All households receiving the assisted
collections had been contacted to confirm that the service was still required,
informal arrangements were being formalised.
·
Problems associated with green bins and
potential compensation were being discussed at Corporate Executive Team level
and would follow the democratic process for resolution.
·
The service would be happy to arrange another
visit to the waste centre in the new year to show members how the logging
system worked.
·
It was expected that the Corporate Director’s
focus would be weaned off the waste collection service over the next few weeks.
·
At least one person who had been assisting the
service temporarily had applied for a permanent position.
·
There was still one caged vehicle in operation
for rural areas, that vehicle had been adapted to keep the various waste
streams separate from each other.
·
There would be an ongoing communication with
residents regarding waste separation and cleansing etc.
·
Routes for electric vehicles were planned
predominantly around urban areas.
·
Whilst the request to Cabinet was for resources
up to a maximum of £1.299m dependent on the level of support from Welsh
government it would not necessarily require that much.
The Committee requested that the level of support received
from Welsh Government was shared with members as soon as it became available
and that a review of the new rounds be presented to a member briefing shortly
after they were implemented.
It was also proposed that a report be
brought back to Communities Scrutiny Committee in February / March 2025 for
review.
RESOLVED that:
- an all member briefing be held two weeks after the roll
out of the new route to review its progress;
- a report be brought
back to Communities Scrutiny Committee in either February or March 2025 to
assess the impact on the additional resources on the effectiveness on the
Service and
- That the Committee
confirms that it has taken account of the Wellbeing Impact Assessment
(appended to this report) as part of its consideration.
Supporting documents:
- 2024_10_24_Communities Scrutiny, item 5. PDF 136 KB
- App 1 Cabinet Report Waste and Recycling Service, item 5. PDF 150 KB
- App 1a WBIA, item 5. PDF 275 KB
- App 1b Summary of other waste issues, item 5. PDF 121 KB