Agenda item
SUSTAINABLE COMMUNITIES FOR LEARNING - ROLLING PROGRAMME
- Meeting of Cabinet, Tuesday, 23 April 2024 10.00 am (Item 6.)
- View the declarations of interest for item 6.
To consider a report by Councillor Gill German, Deputy Leader and Lead Member for Education, Children and Families (copy enclosed) seeking Cabinet approval to submit the draft Strategic Outline Programme for the Sustainable Communities for Learning Programme to the Welsh Government for their consideration.
Decision:
RESOLVED that Cabinet –
(a) approves the submission of the draft
Strategic Outline Programme for the Sustainable Communities for Learning Programme
(Appendix 1 to the report) to the Welsh Government for their consideration, and
(b) confirms that it has read, understood and
taken account of the Well-being Impact Assessment (Appendix 3 to the report) as
part of its consideration.
Minutes:
Councillor
Gill German presented the report seeking Cabinet approval to submit the draft
Strategic Outline Programme (SOP) for the Sustainable Communities for Learning Programme
to the Welsh Government (WG) for their consideration.
The
WG had changed its approach to delivering the Sustainable Communities for
Learning Programme (formerly 21st Century Schools), moving away from 5 year
bands of investment to a more flexible approach over a longer 9 year time
period divided into 3 blocks of 3 years each.
Local authorities had been asked to update their SOP under the new
structure with projects essentially ready for business cases to be brought
forward in the first 3 years, projects being developed and going through the
statutory consultation in the second 3 years and pipeline projects for the
final 3 years. The programmes would be
reviewed every 3 years.
The
proposals and reasoning behind phasing the Council’s school investment over the
next 9 years had been set out in the report and by the Lead Member, in brief –
· due
to delays the 4 Band B projects (Ysgol Plas Brondyffryn, Ysgol Pendref, Ysgol
Bryn Collen/Ysgol Gwernant, and Denbigh High School) would not be delivered within
the original timescales and given current financial pressures there was a need
to reconsider what was affordable over what time period. It was recommended the
commitment to developing all 4 Band B projects be retained and incorporated
into the new SOP, but the development timescales be reprofiled to spread out
the revenue pressures over a longer period
· an
additional project was also proposed to be included in the SOP to be brought
forward in the first 3 year timeframe relating to a small extension at Ysgol y
Castell which was at risk due to increased costs; its inclusion in the
programme would allow it to proceed with no borrowing requirements by the
Council with the match funding required being provided by Section 106 developer
contributions
· the
Council was required to make a capital contribution to the current Band B
projects which would be funded via prudential borrowing. If all Band B projects rolled over to the
first 3 years it was likely that further cuts to services, including delegated
school budgets, would be needed to fund the borrowing costs, hence the proposal
to stagger that borrowing over a more manageable timeframe
· as
Ysgol Plas Brondyffryn was the most advanced project it was proposed that
investment in that school be sought in the first 3 year period with the less
advanced Band B projects being included in the second 3 year period (2027 –
2030), and in the final 3 year period (2030 – 2033) consideration would be
needed to progress further ambitions dependent on the financial position at the
time of the first review in 2027. It was
accepted that the proposal would be a blow to those schools who may need to
wait longer for the improvements needed but work would continue towards
realising those ambitions as quickly as possible including any interim work
that could be progressed in the meantime.
The
Corporate Director: Social Services and Education, Head of Education and
Principal Manager – School Support were also in attendance for this item. The Head of Education added that there were
difficult and unpopular decisions to be made but given the financial climate it
was heartening that the Council’s ambitions for the investment in those schools
was being retained over the next number of years. WG’s expectation for the first 3 year period
was for projects that were deliverable within that period to be progressed
which was why Ysgol Plas Brondyffryn had been proposed given the project was
currently at RIBA Stage 3.
Cabinet
considered the contents of the report and the implications for schools in the
programme as a result of the recommendations.
Councillor Julie Matthews highlighted the urgent need for the specialist
provision provided by Ysgol Plas Brondyffryn.
In response to questions, it was confirmed the school was currently
oversubscribed with a waitlist and pupils were also waiting for formal
assessments and diagnosis to be able to access the provision. The wider added pressures on mainstream
schools were also highlighted and potential for placing more children out of
county. The project would allow demand
for that provision to be met via the increase in capacity from the current 133
pupils to an overall capacity of 220 pupils.
It was noted that 16% of those current pupils resided outside of the
county.
Councillor
Rhys Thomas highlighted a number of risks and uncertainties arising from the
proposed rolling programme of projects including planning permission for Ysgol
Plas Brondyffryn, potential legal challenge to the process as set out in the
School Organisation Code, lack of buy-in from Denbigh Member Area Group, local
neighbouring school, businesses and organisations that would be impacted as a
result of the proposals, uncertainties around inflation and future WG funding
and political changes. Given those
reservations he felt unable to support the proposals and raised a number of
questions on those matters. Councillor
Gwyneth Ellis considered progression of the programme to be a risk given the
financial predictions in the medium-term which effectively resulted in the
Cabinet having to prioritise projects because schools first on the list were
more likely to be completed. She did not
consider the progression of those schemes which were more advanced to be the
correct way of prioritising projects.
Councillor Emrys Wynne asked for the wording in the Wellbeing Impact
Assessment to be strengthened to make it mandatory for the building to deliver
bilingual signage within the school.
The Lead Member and officers responded to the
issues raised as follows –
· there
was a risk associated with securing planning approval for the preferred site
for Ysgol Plas Brondyffryn and if planning permission was refused the matter
would need to be reconsidered by Cabinet and the SOP resubmitted
· any
resubmission of the SOP would need to fulfil WG’s criteria and meet the
requirements of the grant for the next stage; there was an agreement with WG
and a funding allocation to Denbighshire for the project
· the
programme for Band A projects was given as an illustrative example where the
final programme had been different to the original approved programme and a
partnership approach was taken with the WG which had allowed projects to be
changed during the lifetime of that programme to successfully deliver projects;
that approach would also be taken with the SOP to reflect changing priorities
· in
terms of the potential for rising inflation, increased costs, and impact on
projects in future years no specific assurances could be given as that
situation was unknown, but assurance was provided that officers would work with
stakeholders with a view to fulfilling the intention of the SOP
· it
was noted that many of the risks and uncertainties raised were common to all
capital projects and those risks needed to be weighed up and a decision made
· WG
had been clear in their requirements that priority should be given to projects
that could be delivered and completed in the first 3 year period. The Ysgol Plas Brondyffryn project met the
expectations of WG for completion within timescale and the budget was in place,
and there was a need to expand capacity for specialist provision with
implications on pupils, other schools, and costs if those needs could not be
met. If any of
the other projects were to be prioritised, they would not be completed within
the timeframe required by the WG
· agreed
to look to change the wording in the Wellbeing Impact Assessment to make it
clear that bilingual signage in schools was a requirement.
The
Leader opened the debate to non-Cabinet members. Councillor Delyth Jones pointed out the need
for both pupils with Additional Learning Needs and pupils in schools in
deprived areas with unsuitable learning environments, and the difficulties in
prioritising one cohort over another, and raised questions regarding the
progression of the projects and timescales provided. Councillors Mark Young and Pauline Edwards
elaborated on emails they had sent to Cabinet setting out their concerns
regarding the report recommendations and any delay to the progression of Denbigh
High School and Ysgol Pendref respectively given the current building
conditions and urgent work required and the impact it would have, particularly
in an area of deprivation. Councillor
Young raised a number of questions regarding the funding elements and member
engagement and asked that the Cabinet decision be deferred pending further
debate and consideration by the local members and wider council. Councillors Merfyn Parry and Huw
Hilditch-Roberts also voiced their views and concerns regarding the lack of
engagement and buy-in from local members and rationale for the recommendations,
with Councillor Hilditch-Roberts suggesting that the rationale be based on the
pupil need per head.
The
Lead Member and officers responded to the questions and comments, together with
further supplementary questions raised as follows –
· all
schools put forward in the SOP had need of investment and ambitions for those
schools remained as priority areas but the WG guidance was clear that the first
3 year period must include the most advanced and ready to be brought
forward. Work would continue on those
other projects during the first 3 year period to ensure they could move forward
at pace in the second 3 year period
· it
would take around 111 weeks for projects to reach RIBA Stage 3 and be
construction ready; the earliest Ysgol Pendref could start work on site would
be 2026 and the proposal was to start Spring 2027, the earliest construction
could start on Denbigh High School site would be April 2027, and on that basis,
there was no long delay in commencement of the projects
· the
level of need and deprivation in the area was accepted and support was provided
through Community Focused Schools and other funding elements
· there
were various reasons why projects developed at different rates, particularly
given different pathways were followed and evolved as part of the process which
were beyond the capacity and control of the Council
· all
projects had been carried out in parallel.
Delays to the Ysgol Pendref project had been due to issues over site
selection resulting in the decision to remodel the existing school and the
Denbigh High School project was linked to the Ysgol Plas Brondyffryn
project. Reference was also made to the
needs of Ysgol Bryn Collen / Ysgol Gwernant in Llangollen who were also sharing
many facilities
· there
had been numerous discussions at Denbigh Member Area Group regarding the school
projects. The current decision around
the SOP was a Cabinet decision and the same processes had been followed
previously for Band A projects – the decision had not been called into scrutiny
or submitted to scrutiny. The various
elements of the wider rolling programme had been to Cabinet four times since
April 2022
· if
all projects were progressed at pace the impact of the prudential borrowing
required meant that savings would need to be found elsewhere which would
inevitably impact on schools’ budgets; there was also a need to meet the WG’s
expectations in order to secure the necessary match funding for the projects
· the
reduction in the maintenance grant for school buildings was also a challenge
and discussions were ongoing to explore the possibility of using revenue
maintenance funding as the match funding element of the programme for Denbigh
High School so there was no borrowing cost to Denbighshire
· the
Council met all of its legal obligations in respect of the school estate with
regular condition surveys and maintenance and refurbishment work carried
out. There was a process which was being
followed as sedulously as possible
· no
project had been delayed to date due to budgetary decisions. The current recommendation was to widen the
length of time taken to complete the Band B projects due to the impact of
borrowing costs on the revenue budget
· reiterated
if a decision was made to prioritise a different school project in the first
phase it would not be possible to deliver the project in the first 3 year
period
· between
2018/19 – 2023/24 around £1.5m had been spent across all sites with the
majority of spend on Ysgol Plas Brondyffryn due to the work on the business
case and reaching the planning stage, and most of that had been funded by the
Council. Usual practice was that design
costs were used for match funding later in the project so that funding was
effectively claimed back at a later stage
· if
previous considerations had been based solely on the number of pupils impacted
no smaller rural schools would have been built and many rural schools would
have closed. There had been many considerations for the original Band B
projects including condition, suitability, capacity and sufficiency and the
impact. Demand for specialist provision
was not being met with pupils waiting for places in Ysgol Plas Brondyffryn.
Whilst accepting the condition of the other schools, all pupils had a school place
with good teaching and learning meeting their needs.
The
Leader accepted that it was an extremely difficult decision which had to be
made in the context of the serious financial challenges facing the authority
and the borrowing impact. All of the school
projects had a valid case in terms of need, and he thanked everyone for their
views and contributions to the debate.
RESOLVED that, by majority vote, Cabinet –
(a) approves the submission of the draft
Strategic Outline Programme for the Sustainable Communities for Learning
Programme (Appendix 1 to the report) to the Welsh Government for their
consideration, and
(b) confirms that it has read, understood and
taken account of the Well-being Impact Assessment (Appendix 3 to the report) as
part of its consideration.
At this point (12.15 pm) the meeting adjourned for a
refreshment break.
Supporting documents:
- SUSTAINABLE COMMUNITIES FOR LEARNING, item 6. PDF 145 KB
- SCL - Appendix 1 Rolling Programme Projects, item 6. PDF 226 KB
- SCL - Copy of Appendix 2, item 6. PDF 78 KB
- SCL - Appendix 3 impact assessment_, item 6. PDF 108 KB