Agenda item
FLOOD RISK MANAGEMENT RESPONSIBILITIES IN RELATION TO THE RHYL CUT AND PRESTATYN GUTTER
To consider a report by the Council’s Flood Risk Manager (copy attached) which presents the Committee with the conclusion of the joint study, led by Natural Resources Wales (NRW), into potential improvements in the management of the Rhyl Cut and Prestatyn Gutter. The report seeks members’ feedback on the study’s findings and conclusions.
11:05am – 12:05pm
Minutes:
The Lead Member for
Waste, Transport and the Environment, supported by the Head of Highways and
Environmental Services (HHES) and the Flood Risk Manager presented the Flood
Risk Management Responsibilities in relation to the Rhyl Cut and Prestatyn
Gutter report (previously circulated) to the Committee. In addition to
Denbighshire County Council officers three representatives from Natural
Resources Wales (NRW) were in attendance for the discussion - Keith Ivens,
Daniel Bryce-Smith and Paula Harley.
The report
presented conclusions of the joint study, led by NRW, into whether improvements
could be made to the management of the Rhyl Cut and Prestatyn
Gutter, adjacent
drains and sewers – a complex network of watercourses in the Rhyl and Prestatyn
area, which comprised of natural watercourses, some of which had been modified
as well as constructed waterways. The
report also outlined each organisation’s responsibilities in relation to flood
management and flood mitigation.
Following the
flooding that affected parts of Rhyl and Prestatyn in July 2017, NRW commenced
a review of the hydrology, management and maintenance of Rhyl Cut and Prestatyn
Gutter, which are classed as “main river” watercourses. Denbighshire County
Council (DCC) and Welsh Water (WW) agreed to support NRW with the project,
which would also hopefully provide a better understanding of how each
organisation’s assets interact, particularly during times of heavy rainfall.
The project was carried out in three phases.
(i)
Phase 1
which involved a flood risk modelling study, to give NRW a better understanding
of the hydrology of the river catchments.
(ii) Phase 2 that resulted in a catchment
management report, which took a broad overview of the management of Rhyl Cut
and Prestatyn Gutter and the areas surrounding the two watercourses.
(iii) Phase 3 built upon the recommendations
within the Phase 2 management report and involved discussions within NRW’s
operational maintenance teams
to consider the impacts of maintenance within different sub-reaches of the
watercourses. There was still some work to carry out in terms of producing a
comprehensive maintenance and management plan and this would require a process
of public and stakeholder consultation.
The Committee was shown a presentation by
NRW officers outlining the work which had been carried out by NRW, DCC and WW.
The first three stages had now been delivered, the findings of which would
allow flood risk management teams to develop long term management and
maintenance strategies.
The approach which was taken for the third
phase was an evidence-based one using detailed hydraulic modelling. This work had included an assessment on the
impact of channel vegetation (roughness), bed levels, and blockages at key
locations. This has improved NRW’s understanding of localised maintenance and
informed efficient risk-based management techniques within each sub-reach.
During the third phase NRW had also been
able to identify potential opportunities for capital interventions to reduce
flood risk. It recognised the current risk of flooding to the communities of
Prestatyn and Rhyl and has plans in place to undertake a full appraisal of
options for improvement works, commencing with a Strategic Outline Case (SOC)
in 2022.
During the ensuing
discussion:
·
members thanked officers for the work which had been
carried out, however some felt that aspects of the work should have been
carried out sooner.
·
NRW confirmed that issues such as the maintenance of
property gardens and walls and the need to safeguard debris etc, from entering
or falling into the Rhyl Cut and causing blockages was a matter for the
riparian landowners i.e. individual property owners. NRW were not the owners of the Cut, it had
permitted powers insofar as to undertake work to mitigate the risk of flooding
from the watercourse. For this purpose,
NRW had access points at certain locations along the Cut to enable it to gain
access to undertake the necessary maintenance work. This avoided the need for it to seek the
agreement of multiple riparian landowners in order to undertake essential flood
maintenance work.
·
The Monitoring Officer confirmed that he would
liaise with the Council’s Legal Services Department to confirm whether the
Council was a riparian land owner for any part of the Rhyl Cut or Prestatyn
Gutter.
·
NRW officers confirmed that the annual programme of
flood maintenance work was carried out on both the Cut and Gutter from late
August onwards, once the bird nesting season had ended. The maintenance worked commenced on the lower
reaches working up towards the higher reaches
The
Committee:
RESOLVED subject
to the above observations to:
(i)
receive the
contents of the report, appendices and presentation; and
(ii) seek Denbighshire County Council officers to
establish whether the Council itself was a riparian landowner for any part the
Rhyl Cut or the Prestatyn Gutter.
Supporting documents: