Agenda and draft minutes
Venue: via video conference
Media
Webcast: View the webcast
No. | Item |
---|---|
APOLOGIES Additional documents: Minutes: There were no apologies received. |
|
DECLARATION OF INTERESTS PDF 116 KB Members to declare any personal or prejudicial interests in any business identified to be considered at this meeting. Additional documents: Minutes: Councillor Ellie Chard declared a personal interest in agenda item 7 – Approval of the Statement of Accounts 2020/21 - as she was a member of Clwyd Pensions Fund. |
|
URGENT MATTERS Notice of items, which in the opinion of the Chair should be considered at the meeting as a matter of urgency pursuant to Section 100B(4) of the Local Government Act 1972. Additional documents: Minutes: There were no urgent matters raised. |
|
To receive the minutes of the Governance and Audit Committee meeting held on 22 September 2021 (copy enclosed). Additional documents: Minutes: The minutes of the Governance and Audit committee held on 22 September 2021 were submitted. RESOLVED that the minutes
of the Governance and Audit committee held on 22 September 2022 be received and
approved as a correct record. |
|
CARE INSPECTORATE WALES - ASSURANCE CHECK 2021 PDF 212 KB To receive a report on
the findings of the Care Inspectorate Wales (CIW) assurance check of
Denbighshire County Council undertaken 28 June to 2 July 2021 (copy enclosed). Additional documents:
Minutes: The Corporate
Director Communities (CDC) presented the Care Inspectorate Wales (CIW)
Local Authority Performance Review (previously circulated). The CDC introduced
Sian Roberts from Care Inspectorate Wales to the committee. It was explained
that Sian was the authorities lead inspector, an excellent working relationship
had been established. Sian oversees both children’s and adult social care
issues for Denbighshire. The report
summarised the findings of the CIW assurance check of Denbighshire County
Council undertaken 28 June to 2 July 2021. The purpose of the assurance check had
been to review how well local authority social services continued to help and
support adults and children with a focus on safety and well-being. Due to the
pandemic it was stressed the normal arrangements for oversight and scrutiny had
been altered to reflect the restrictions. It was important to note that many of
the CIW colleagues returned to frontline work and supported health and social
care delivery in the pandemic. The CDC wanted to express her thanks to all CIW colleagues,
it had been recognised and valued across all Wales. As the
restrictions eased, CIW officers felt that it was important to conduct
assurance check to assure authorities and CIW that services were being delivered
appropriately and safely. The letter summarised the findings of the CIW
assurance check undertaken 28 June to 2 July 2021. The CDC highlighted
a number of positives stated within the letter. The recognition of the positive
culture and improvements within safe guarding was given particular importance. The letter also
acknowledged areas of improvement for the service. Confirmation
that audits had been temporarily halted during the pandemic, but have reinstated.
The report acknowledged the challenges in recruitment throughout the service.
The CDC stressed the comment that staff in Denbighshire are a credit to
themselves and to the authority. The Lead
Member for Well-being and Independence stressed the challenges faced by the
service during the pandemic. She thanked the CIW officers for conducting the assurance
check and producing the report. The Chair on
behalf of the Governance and Audit committee wanted to thank the staff and
officers for supporting the service and the community during the Covid-19
pandemic. During the
discussion, officers and the CIW representative expanded on the following: ·
Recruitment
was noted as a nationwide issue. A recruitment day had been held to provide additional
information. Officers were doing all they could to recruit individuals into the
service. Work to achieve a higher status and pay for employees in the service within
Denbighshire was ongoing. The term ‘grow your own’ was made with reference to
professional roles. It is an option the authority was exploring. Partnership work
with Glyndwr University to explore the options had begun. Members heard that
the process did have a number of problems but did present challenges. ·
Work
with colleges and sixth forms to aid recruitment had taken place. Work locally,
regionally and nationally to promote the sector as a professional career for
individuals was ongoing. ·
Part of
the Welsh Government hardship grant had been utilised to purchase technology. I-pads
were purchased and placed in some extra care services and supported living
schemes. Enabling individuals to maintain contact with friends, family and the
officers. ·
Members
were pleased to note that support for staff had been provided during the pandemic.
It was emphasised that it was a corporate wide approach to supporting our staff
was adopted. ·
The CDC
provided members with some further information about referrals. It was acknowledged
it was an area that needed further work and improvement. Managers and officers
were exploring avenues to address the concerns raised in the CIW check. Members discussed the need ... view the full minutes text for item 5. |
|
CORPORATE RISK REGISTER REVIEW - SEPTEMBER 2021 PDF 151 KB To receive a report on
the September review of the Corporate Risk Register (copy enclosed). Additional documents:
Minutes: Lead Member for Finance,
Performance and assets along with the Strategic Planning & Performance Team
Leader (SPPTL) presented the Corporate Risk Register Review, September 2021
(previously circulated). Members heard that the Corporate
Risk Register was regularly reviewed and the report had been presented at by
CET, SLT and Cabinet prior this committee and Performance Scrutiny Committee. The report highlighted changes made to the register. A number of changes had been made to risks including; scoring, wording and an additional two risks identified. The Lead Member guided members through the summary within the report which identified the changes. It was highlighted Risks 18 and 35 were to be merged going forward and the likelihood score would be increased from D2 to C2 score. The two new risks identified - Risk 47: The risk that the new North Wales Corporate Joint Committee and
Risk 48: Recruitment and retention issues. The two new risks had been escalated to the Corporate Risk Register and
summarised within the Register. At this juncture the SPPTL stressed the report was presented
to the committee annually to assure members that the corporate risk processes
were being robustly applied. This review followed a recent internal audit review regarding risk management including recommendations from the audit had been put forward. One of the recommendations had been to include a direction of travel for each of the risks. There was still an amount of work to be done in that regard which would be taken forward in the next review. Work had started on performance measures to assess how well
risks were improving. This work was still in its infancy and further work with
risk owners would be needed. Included in the review had been a thorough
assessment of risk appetite. During discussions, the following points were raised: · Risk 11 – the risk was concerned with the authorities inability to respond. The SPPTL stated he was satisfied the risk was still relevant. · Risk 44 - Ash dieback action plan report was expected by March 2022. · HR had currently begun a piece of work on work force planning with each individual service to go through staff retention and recruitment concerns and issues. An action plan for each service would then be produced. The Corporate Director for Communities highlighted, Covid had brought challenges and opportunities. One of the changes that had been observed was the opportunity for individuals to re-evaluate work life and personal life with individuals making decisions such as early retirement and changes in careers as a result of this. · Risk 36 – confirmation that the residual risk score had been downgraded from B2 to C2. The Risk Score was reflective at the time the register was updated. Members heard the authority held a separate Risk Register for Brexit. A future piece of work to dismember the Brexit Risk Register was needed to ensure that risks that are still relevant are evaluated and included in the Corporate Risk Register if necessary. RESOLVED that the
Governance and Audit Committee are assured that the council’s risk management
process was applied correctly.
|
|
APPROVAL OF THE STATEMENT OF ACCOUNTS 2020/21 PDF 141 KB To receive a report by the Head of Finance and Property on the approve the statement of accounts and ensure that it complies with approved accounting standards (copy enclosed). Additional documents:
Minutes: The Lead member for Finance, Performance and Strategic Assets presented The Statement of Accounts 2020/21 (previously circulated) for approval the council has a statutory duty to produce a statement of accounts that complies with approved accounting standards. The audited accounts have to be formally approved by elected members on behalf of the council. The
financial statements for 2020/21 were approved, subject to audit, by the Head
of Finance and Property on 2nd August. The draft accounts were presented to
Corporate Governance Committee on 22nd September 2021 and were open to public
inspection from 2nd September to 29th September. The approval of the audited
accounts had been delegated to the Governance and Audit Committee. The
Statement of Accounts were produced in compliance with the International
Financial Reporting Standards (IFRS). The Chartered Institute of Public Finance
& Accountancy (CIPFA) produced the IFRS based Code of Practice on Local Authority
Accounting and the council has produced the 2020/21 accounts in compliance with
the Code. It was
stressed this was the first year that the authority had to complete group
accounts, with the accounts from DLL incorporated in the overall accounts. The
timetable for completion of accounts had been delayed due to covid, the final
deadline for approval and signing off of the accounts was 30 November 2021. The Head of
Finance and Property Service (HFPS) expanded on the introduction by
highlighting the stressful process to achieve the accounts by the deadline. An
update report will be presented at the next committee meeting to summarise the
work on next years’ timetable would be presented. Work with DLL would continue
to ensure accounts are received in time.
He thanked the work of officers and Audit Wales representatives. Matthew
Edwards, Audit Wales representative echoed the thoughts of HFPS. The close
working with the finance team had been positive. The report set out the key
findings from the audit of Draft Statement of Accounts. He confirmed once the
committee approved the finance statements, the Auditor General would issue an
unqualified audit report. Members
heard it was the responsibility of the Auditor General to provide the authority
with an opinion on the financial statement. That opinion covered two key
aspects: ·
Whether
in all material respects they give a true and fair view of the financial
position of the authority for the financial year, and ·
Whether
they have been prepared in accordance with the CIPFA code of practice of local
authority accounting. The audit
identified seven uncorrected misstatements, all detailed within the report. The
International Standards of Auditing required Audit Wales to formally request
reasons as why they have not been corrected.
Those reasons had been provided in the report. Audit Wales
highlighted a need for the authority to have an efficient and effective
accounts closure process for the accounting and recording of property, plant
and equipment. The Chair on
behalf of the committee thanked the officers and representatives from Audit
Wales for the hard work that had been done to produce the accounts. It was a
difficult year and the teams had worked extremely hard to produce the accounts
to the deadline. General
debate – · The HFPS confirmed it was a small team of finance officers that worked on the accounts. It had been recognised that there was a limited number of staff that had the qualifications to be able to work on the accounts. It was noted a number of staff may retire or leave at similar times. A trainee scheme was in place but it took 4 years for an individual to become qualified. The Monitoring Officer echoed the HFPS statement in supporting individuals to become ... view the full minutes text for item 7. |
|
At this
juncture (11.10 am.) there was a 15 minute break. Meeting reconvened at 11.25 a.m. |
|
FINANCIAL SUSTAINABILITY ASSESSMENT PDF 122 KB To receive
the Audit Wales’s Financial
Sustainability Assessment report relating to Denbighshire County Council (copy
enclosed). Additional documents:
Minutes: The Audit Wales representative David Wilson guided members through the report (previously circulated). He stated the report overall was positive. Highlighted within the report had been the covid funding received and the impact that had on the Council’s finances overall. Members were reminded that reports had been prevented during the year on the impact of covid. Stated in the report was the Audit Wales opinion that the authority had a good record of managing its budget, with further aspiration to improve its financial position. The Audit Wales representative guided members through the contents included in the Wales Audit report. Contained within the report was the management response to the one recommendation on the budget variation work. The Head of Finance confirmed the budget process that had been implemented this financial year would resolve the issue around identifying pressures in services. The Chair thanked the Audit Wales representative and
officers for the detailed report. During the
discussion the Audit Wales representative and the Head of Finance expanded on
members enquiries: ·
Additional funding of £1.6mil had been received at
the end of the year. Each local authority received additional funding. Attached
to the funding had been two headlines- savings that had not been achieved and
digital technology. The additional funding was received at the end of the year
and was not linked to expenditure. The authority did not have to show a failure
in achieving a sum of its saving or the digital costs. The additional funds were provided by Welsh Government; the amount had been decided by Government. ·
The modified loan reserve was created when previous
loans where collated and refinanced, the reserve had been created by overpayments
made on those loans. The funds in the reserve would be fed back into the
reserve accounts to contribute to the future higher payments for the refinanced
loans over the next 20 years. Reserves are constantly reviewed. The usable
reserves were available if the authority was required to reassign to a service.
·
The term ‘impactful service change’ referred to the
authority meeting the savings target most years without too much impact on direct
service provisions. At some stage it was noted the council would have to make
some savings that would have an impact on direct services. Members thanked the officers and representatives for the detailed responses RESOLVED that members note the Financial Sustainability Assessment report and considered
the management response. |
|
INTERNAL AUDIT UPDATE PDF 141 KB To consider a report by the Head of Internal Audit (copy enclosed) updating members on Internal Audit progress. Additional documents:
Minutes: The Chief Internal
Auditor (CIA) introduced the report (previously circulated) updating members on
the Internal Audit Team’s progress in terms of its service delivery, assurance
provision, reviews completed, performance and effectiveness in driving improvement.
The report provided information on work carried out by Internal Audit since the last committee meeting. It allowed the committee to monitor Internal Audit’s performance and progress as well as providing summaries of Internal Audit reports. Confirmation that 5 Audits and 3 follow up reviews had been completed since the last committee meeting. It was highlighted that 1 of the 5 completed audits had received a low assurance the audit report had been attached as appendix 2 to the report. Of the 3 follow up reviews completed, 2 had been awarded a medium assurance and details had been included in the Internal Audit Update report. One follow up report was given a low assurance rating, details of that review where included as agenda item 10 on Contract Management. Confirmation that the Senior Auditor position had been filled through a secondment of an existing member of the team, which in turned created an Auditor vacancy. Members heard the secondment of the Senior Auditor to Trace, Test and Protect (TTP) had been further extended to June 2022. Members were reminded details of each of the audits
had been included as appendix 1 to the report. A brief background of each audit
was presented to the committee. The audit conducted on Denbighshire Leisure
Limited – Governance & Contract Management was a high level review of the
governance arrangements and the management of key risks following the
transition. The overall assurance was
that the governance arrangements in place with Denbighshire Leisure Limited
were robust. Further details of the audit were detailed in the report. The CIA
guided members through the detailed report. Appendix 2
provided members with the Internal Audit of Exceptions, Exemptions and
Variations from the Contract Procedure Rules (CPR). The purpose of the review had
been to provide assurance that contract exceptions, exemptions, and variations were
authorised and used appropriately in line with Contract Procedure Rules. The
CIA introduced the Senior Auditor who conducted the audit. The Senior Auditor
(SA) provided further details of the audit. The Legal and Procurement team had actively
encouraged the audit. The audit sought to assess any effect the pandemic may
have had on the use and prevalence of exception and extension requests.
Confirmation that a sample of decisions from the previous 2 financial periods.
The contract procedure rules were detailed with the provisions for granting
exceptions and exemptions and variations were clear and concise. It was felt
the pandemic did not increase the volume of directly awarded contracts or
extensions. There were
four issues raised during the audit, details of each had been included in the
report. During the
discussion – · Exceptions were contracts that had been awarded without going through the tendering process. · Teckal exemption was a name of a case that established the principal that it was possible for a public sector organisation to enter into a contract with an entity that it controlled provided that there was no private sector involvement in that entity, the public body was able to demonstrate that it retained the same level of control over the said entity as it would of one of its own service departments and at least 80% of the turnover of that entity was related to work or services being performed for that public body. · Members were reminded that the authority held a joint procurement service with Flintshire County Council (FCC). The SA confirmed she had obtained information on the ... view the full minutes text for item 9. |
|
INTERNAL AUDIT FOLLOW UP OF CONTRACT MANAGEMENT PDF 124 KB To receive an update report on progress in implementing the action plan that accompanied the
Internal Audit report on Contract Management (copy enclosed). Additional documents: Minutes: The Chief
Internal Auditor (CIA) guided members through the second Internal Audit follow
up report (previously circulated). The report provided members with an update
on the progress in implementing the action plan that accompanied the Internal Audit
report on Contract Management. The original audit report was presented to the
committee July 2020, at that meeting the committee requested a revised action
plan to reflect key changes which was presented in January 2021. The first
follow up was reported to committee in July 2021 with members requesting a
second follow up report. The Senior
Auditor presented to members her findings from the second internal audit
review. Members heard the assurance rating had remained as a low assurance a significant
amount of progress in key areas had been made. One area noted was the approval
of dedicated contract management resource. Confirmation
that the contract management forum had been established with service wide representation.
The first meeting of the forum had taken place in early November. A forward
work programme for the forum had been established, it identified and assess
additional training needs across the variety of services. The contract
management framework had been approved by SLT and was in the process of being
rolled out to services. Prior to its implementation to services the forum would
conduct rigorous tests on the framework to ensure it is fit for purpose. The assurance
rating had remained as a low assurance primarily as a number of actions from
the original action plan remained outstanding. The outstanding actions had
mainly been linked to the implementation and embedding of the contract management
framework. It was stressed in the first follow up some of the revised dates had
been ambitious and challenging to achieve. The
Monitoring Officer (MO) suggested that a follow up review was presented to
committee following review of the outstanding actions. Members heard that
within the Procurement team, a systems officer had been recruited. Unfortunately,
the service was still without a procurement manager. The CIA
confirmed that a review was scheduled for June 2022. A follow up report could
be presented to committee following this review. RESOLVED
that members note
the contents of the follow up report on Contract Management and a further
follow up report be included in the committee forward work programme follow the
internal audit review. |
|
PROGRESS REVIEW OF THE NORTH WALES GROWTH DEAL - NORTH WALES ECONOMIC AMBITION BOARD PDF 120 KB To receive
for information a report Audit Wales’s
Progress Review of the North Wales Growth Deal – North Wales Economic Ambition
Board (copy enclosed). Additional documents:
Minutes: The Chair introduced David Wilson Audit Wales to present the report (previously circulated) to the committee. Members were reminded that the Council had been asked to support the growth deal, the support was sought and received early 2021. Included in the review was an examination of the progress made by partners to prepare for delivery of the growth deal including the portfolio of management office, the support from Gwynedd Council provided to the process and the various groups and boards that had been set up to support the deal. The report was purposely quite descriptive. Audit Wales officers stressed the importance of being able to describe how the process worked to incorporate the 6 local authorities and private sector to work together. Positive comments on the progress that had been made where included in the report but recognition of further work required was made. No concerns regarding the operation of the growth deal were raised. The portfolio management office had provided a detailed management response and had been included for members’ reference. The Chair thanked the Audit Wales Representative and noted the assurance from Audit Wales on the progress of the North Wales Growth Deal. RESOLVED, that members
note the contents of the information report. |
|
AUDIT WALES' WORKPLAN & TIMETABLE PDF 120 KB To receive a report on Audit Wales work plan and timetable (copy enclosed). Additional documents: Minutes: The Chair Matthew
Edwards and David Wilson, Audit Wales to present to members the Audit Wales’
Workplan and timetable. Members were guided through the report (previously
circulated). Matthew Edwards updated members on the financial audit work. An emphasis was made on the impact on the authority’s financial team to complete and audit the accounts, which in turn would impact on the Audit Wales work – Certification of the Council’s Grant claims and returns 2020/21. Assurance was provided to member that most of the deadlines would be achieved. The area of concern was the Non-Domestic Rates return claim deadline. It would not be met; it was stressed that a number of authorities in Wales had failed to meet the assigned deadline. Confirmation that Welsh Government had been made aware of the position and priority to this work had been given. A report back to committee would be provided following any outcomes in the spring. David Wilson guided members through the performance audit work completed and scheduled. It was positive to note that the work scheduled for Denbighshire was on track to be completed by the end of March. Members
thanked the officer for the report. RESOLVED that members note the contents of the report. |
|
GOVERNANCE AND AUDIT COMMITTEE WORK PROGRAMME PDF 298 KB To consider the committee’s forward work programme (copy enclosed). Additional documents: Minutes: The Governance
and Audit Committee’s Forward Work Programme (FWP) was presented for
consideration (previously circulated). It was
agreed to amend the FWP as following: ·
Audit Wales review on Cyber Resilience update included on the January
or March 2022 meeting; ·
Internal Audit Strategy 2022/23 report – March 2022; ·
Draft Annual Governance Statement report – April 2022; ·
Internal Audit Annual report – June 2022; ·
Annual Whistleblowing report – March 2022; ·
Annual report of RIPA – June 2022; ·
Follow up reports from the Internal Audit reports on Contract
Management and Exceptions and Exemptions – July 2022; ·
Update on uptake of Proactis – March/ April 2022. The
Head of Finance and Property Services stated he would discuss the budget
reports with the Community Staff to include in the FWP. RESOLVED that, subject to the inclusion
of the above additions the Governance and Audit Committee’s forward
work programme be noted. |